Albany Times-Union takes a look at the I-88 Collapse

In this past Sunday's (August 20) Albany Times-Union ran a series of three articles covering the I-88 culvert collapse on June 28.

Rebuilding in the Face of Tragedy - Covers the efforts of the emergency repair team that has worked non-stop since July 2nd to repair the culvert, cover with fill, and pave the highway. They hope to have the westbound lanes reopened by Labor Day.

Truckers' deaths on I-88 still resonate - Tells the story of David Swingle's and Patrick O'Connell's fateful ride the morning of June 28.

Traffic's return to old main drag is hardly a boon - Features businesses and residents along the detour route (NY 7). Some are seeing an increase in business while most are not.

Commentary:

Great work in all three articles in looking at the effects of the collapse from multiple story angles. First, the repairs. The culvert that collapsed was 33 years old, it received a 5 of 7 rating in 2004 and "Inspectors reported "corrosion with minor to moderate section loss for the full culvert length" and "minor perforations" near the outlet, as well as "severe erosion beneath the end left concrete slope paving, exposing the outside of the pipe from below the concrete for the full slope length." The state also briefly considered erecting a temporary bridge to carry I-88 traffic while the culvert was replaced, but decided against it.

Second, the stories of both Mr. Swingle and Mr. O'Connell tells more about the details of the foggy and rainy morning of June 28th, and also the family and friends who deeply love and miss both gentlemen.

Finally, the story about residents and business routes is very interesting. NY 7 for many years was the main route to connect Binghamton to Albany and points east. When I-88 opened, NY 7 became a sleepy backroad. Businesses that once thrived on Route 7 either closed or had to look at reative ways to get travelers off the interstate. Now, with NY 7 pushed back into service not every business has seen a boom. In fact, some businesses and most residents can't wait until the Interstate reopens!

Comments

Popular posts from this blog

The story on how the unbuilt US 40 Expressway in Brownsville took 40 years to complete.

For nearly four decades, the four lane US 40 just east of Brownsville came to an abrupt end - shown in the photo above - at Grindstone Road in Redstone Township.   In the late 1960s, what was then the Pennsylvania Division of Highways (PennDOH) extended a new four lane alignment of US 40 eastwards from Broadway Street slightly over one mile to Grindstone Road where an incomplete diamond interchange was built.  Earlier in the decade, PennDOH had built a four lane US 40 in Washington County into Brownsville complete with a new crossing over the Monongahela River known as the Lane Bane Bridge.  This new highway and bridge allowed US 40 to bypass the older Intercounty Bridge and downtown Brownsville. 

After this new highway opened, nothing would happen to it for nearly forty years.  US 40 traffic would use the ramps for this planned diamond interchange and then jog on Grindstone Road briefly before continuing towards Uniontown on the original National Road. 
What is unknown (at least to…

The story of the Boy Scout Ramps on Interstate 79 North in NW Pennsylvania

If you are traveling on Interstate 79 North of Pittsburgh, you may notice the remnants of a set of off and on ramps at mile 100 just north of Exit 99 (US 422).  There's a story behind these ramps.  Forty years ago, these ramps were built specifically for two Boy Scout Jamboree's that were held at Moraine State Park - 1973 and 1977.  The ramps purpose were to provide access to the north shore of Lake Arthur where the bulk of the festivities and campsite for the Jamboree were located.  (Lawrence County Memories has a great write up and map of the festivities on its site.)

Not long after the Jamboree ended the ramps were abandoned.  There are still remnants of the Boy Scout Ramps today.



Above: Sattelite view of the Boy Scout Jamboree Ramps. 
Below: A view of the ramps from I-79 South.



The google street view image above gives a view along West Park Road of where the set of ramps intersected the highway.  The ramps provided direct access to North Shore Drive (which is the right tur…

The few clues of the Northern Durham Parkway

Sometimes when you look through a box of maps for the first time in five years, you come across something you may have easily over looked.  Such was the case when I found a 2004 (so rather recent) map of Raleigh.  This map was made by the Dolph Map Company for WakeMed.  In the Northwestern corner of Wake County, there were two items to the map showing roads that are still not in existence 13 years later.

The road is the Northern Durham Parkway - this is a proposed 19 mile highway from US 501 north of Durham to the Raleigh-Durham International Airport.  The first proposals for this highway date back to 1967 when Eno Drive-Gorman Road was listed on the Durham Area Thoroughfare Plan. (1)  Other proposals called the highway the Northwest and Northeast Durham Loop. (2)  The route would serve as a northern and eastern bypass of Durham almost serving as a near loop.  The route was fought vigorously for three decades by the Eno River Association citing concerns for the the Eno River, nearby n…