Paper: Expecting I-785? It may be awhile.

In Saturday's Greensboro News Record, there was a lengthy article discussing the progress on the Future I-785 corridor. Well make that the lack of progress.

Since the corridor's designation in 1997 - the first Future I-785 Corridor sign were first posted in June 1998, there has been not much done to upgrade current US 29 in Guilford or Rockingham Counties to an Interstate quality highway. US 29/Future I-785 also cuts through the northwest corner of Caswell County.

The cost to upgrade the highway has doubled from an estimated $100 million in 1998 to $200 million today. Most of the upgrading would be on a four lane at-grade section of US 29 from southern Rockingham County to Greensboro. US 29 from Reidsville north to the to the Virginia border is currently a freeway with not as much upgrading necessary.

Currently, the state funding priorities have been towards completing the Greensboro Urban Loop (Interstate 840) and upgrading US 220 to Interstate 73. Interstate 785 may be routed on the Northeast corner of the Greensboro Loop. That section from US 29 southwards to the completed portion of the highway at US 70 is scheduled to begin land acquisition in 2009 followed by the start of construction in 2011. The estimated cost for that section of Interstate 840 is $117 million.

Story:
Road of uncertainty: The proposed I-785 corridor ---Greensboro News-Record

Commentary:
Will Interstate 785 ever exist? That's a good question. Is there a need for an interstate from Greensboro to Danville? Another good question.

Let me answer the second first. There is a need for a freeway NOT an Interstate from Greensboro to Danville. Over 1/2 of US 29 from I-40 to US 360 in Danville is a freeway. Most of it has been built over the last 30 years. Immediately north of I-40, US 29 is an urban freeway with no emergency shoulders, only a concrete barrier with no median separating opposing lanes of traffic. Very narrow and tight ramps to city streets. Also around NC A&T, spectators for sporting events park along what emergency shoulders still remain.

For years on the NC State Highway Map, the Greensboro section of US 29 had been listed as a freeway, it's not any more. Beyond the city limits as you head north towards Reidsville, a center grass median exists, but there are numerous at grade intersections, traffic lights, access roads, etc. that are part of the corridor. This is the section that will need the most upgrading.

If I-785 does come to pass, and I don't think it will be seen for another 20 years if not more, it should be routed along I-840 to eliminate the need, and the cost, to do a major upgrade of US 29 through Greensboro.

But if you aren't going to source funding for the project and there's no urgency to do so, why even try to promote it as a 'FUTURE INTERSTATE CORRIDOR' when nothing is going to be done for another 20 years from now, which is 30 years after the idea was first conceived.

Comments

Popular posts from this blog

The Relief Route That Wasn't: The Never Built I-70 Bypass in the Mid-Mon Valley

In June 1963, a small blurb in the Pittsburgh Post-Gazette read that The Westmoreland Engineering Company was awarded a $24,060 bid to study the proposed construction of Interstate 70 in Westmoreland and Washington Counties.  The study was to see what the construction and right-of-way costs "...to modernize the existing highway to Interstate requirements within eight months." (1)  This small, non-attributed, three paragraph article came less than a decade after the completion of a four lane highway that linked the Mid-Mon Valley to the Pennsylvania Turnpike. This would be the start of a 15 year process to upgrade and improve Interstate 70 - a process that ultimately never produced a single foot of new highway.

This is the story, albeit brief, of the I-70 that never came about.

Background:
What is now known as Interstate70 from Washington to New Stanton began as a connecting highway for the region to the Pennsylvania Turnpike.  Known as the "Express Highway", construct…

A look at Pittsburgh's Saw Mill Run Boulevard

Saw Mill Run Boulevard - Pennsylvania State Route 51 - runs through the narrow Saw Mill Run Valley.  It begins at the intersection of Clairton Road and Provost Road at the City of Pittsburgh Line with Brentwood.  It ends at the West End Circle at the entrance to the West End Bridge.  A four lane highway for its the entire length, Saw Mill Run Boulevard consists of interchanges at the South Portal of the Liberty Tubes and with the Parkway West.  It is an expressway from the Parkway to the West End Circle (West End Bypass).  One of the most well known traffic tie-ups in the Pittsburgh area occurs between Maytide Street and PA 88 (Library Road) which is simply known as 'Maytide and 88.'

History:
Saw Mill Run Boulevard was part of the 1928 Allegheny County 'City Beautiful' bond issue.  The bonds resulted in the creation of Saw Mill Run, Ohio River, Allegheny River and Mosside Boulevards. (1)   After the completion of the Liberty Tunnels in 1924, Downtown Pittsburgh was offic…

The Many Failed Plans of Pittsburgh's Wabash Bridge and Tunnel

The December 27, 2004 opening of the Wabash Tunnel ended over 70 years of proposals and speculation for the use of the over 100 year old facility.  The tunnel, which is now a reversible roadway that is an alternative route for rush hour traffic, saw many failed plans during the 20th Century.  These plans included options for mass transit, converted and new bridges for vehicles, and other forms of transportation.

Brief History:
Constructed in 1902-04, the Wabash Bridge and Tunnel was planned and financed by rail mogul, Jay Gould.  Gould began his "Battle of the Wabash" with the established railroads of the city in 1890.  He would finally emerge victorious, but during that struggle, Gould would see many setbacks that would eventually result in the railroad's bankruptcy in 1908.  On October 19, 1903, when the two ends of the bridge were to be joined together over the Monongahela River, the 109' bridge collapsed; killing ten men.  Construction would resume four days later …