Could I-485 Construction be pushed back to 2015?

If the state's Draft Strategic Transportation Improvement Program for 2009-2015 stays the same, it will.

It is entirely possible that the construction to complete the I-485 loop around Charlotte will not start until 2015, meaning that the loop may not be finished until 2018.

More importantly, the desperately needed widening of I-485 from I-77 to US 521 in Southern Mecklenburg County would also be delayed until 2015, if no changes are made from the draft to the final version.

The official verbiage is "To assist in balancing funds, construction of Segment 'E' delayed from FY 13 to FY 15." Segment 'E' is the missing link from I-77 in Huntersville to I-85 near Concord. The same "to assist in balancing funds" is used in delaying the widening of I-485 in Southern Mecklenburg County from 2013 to 2015.

I would not be surprised that there will be a large uproar from Charlotte, Mecklenburg and regional officials over this delay. The widening has been pushed strongly by transportation advocates in the region for the past few years. Also, communities in the northern part of the county will also be pushing strongly for the completion of the loop between Huntersville and Concord. concord and University officials see the missing link as an opportunity for growth for their communities.

In the past, the two projects (widening and building the missing link) have been at odds for tight highway dollars. With both projects pushed back even further, will both sides work together towards the best solution or will they step over each other wanting the money and perhaps pushing completion and traffic improvements within the loop back even further?

Division Ten Draft 2009-2015 STIP ---NCDOT

Comments

Popular posts from this blog

The Relief Route That Wasn't: The Never Built I-70 Bypass in the Mid-Mon Valley

In June 1963, a small blurb in the Pittsburgh Post-Gazette read that The Westmoreland Engineering Company was awarded a $24,060 bid to study the proposed construction of Interstate 70 in Westmoreland and Washington Counties.  The study was to see what the construction and right-of-way costs "...to modernize the existing highway to Interstate requirements within eight months." (1)  This small, non-attributed, three paragraph article came less than a decade after the completion of a four lane highway that linked the Mid-Mon Valley to the Pennsylvania Turnpike. This would be the start of a 15 year process to upgrade and improve Interstate 70 - a process that ultimately never produced a single foot of new highway.

This is the story, albeit brief, of the I-70 that never came about.

Background:
What is now known as Interstate70 from Washington to New Stanton began as a connecting highway for the region to the Pennsylvania Turnpike.  Known as the "Express Highway", construct…

The Many Failed Plans of Pittsburgh's Wabash Bridge and Tunnel

The December 27, 2004 opening of the Wabash Tunnel ended over 70 years of proposals and speculation for the use of the over 100 year old facility.  The tunnel, which is now a reversible roadway that is an alternative route for rush hour traffic, saw many failed plans during the 20th Century.  These plans included options for mass transit, converted and new bridges for vehicles, and other forms of transportation.

Brief History:
Constructed in 1902-04, the Wabash Bridge and Tunnel was planned and financed by rail mogul, Jay Gould.  Gould began his "Battle of the Wabash" with the established railroads of the city in 1890.  He would finally emerge victorious, but during that struggle, Gould would see many setbacks that would eventually result in the railroad's bankruptcy in 1908.  On October 19, 1903, when the two ends of the bridge were to be joined together over the Monongahela River, the 109' bridge collapsed; killing ten men.  Construction would resume four days later …

Independence Boulevard - Charlotte's First Urban Highway

Today, the major pieces of Charlotte's highway network include the Outerbelt (I-485), Interstates 77 and 85, and the Brookshire and Belk Freeways (I-277), but nearly sixty years ago Charlotte's first major urban highway project would begin.  The construction of Independence Boulevard in the 1940s and early 1950s would give Charlotte and North Carolina its first urban expressway, and would usher in a new era of highway building throughout the state.
With the help of former mayor, Ben Douglas - who sat on the State Highway Commission in the 1940s - the push for building Independence Blvd. began.  In 1946, city residents passed a $200,000 bond issue that would go along with over $2 million in federal funding.  The highway would open in two stages in 1949 and 1950.  When a grade separated interchange was built at South Blvd. and Morehead St. in the mid 1950s, Independence Blvd. was completed. (1)  Although the highway was not a fully controlled access highway, it gave motorists an …