Skip to main content

The I-485 Blame Game

Yes, it's again time for the Interstate 485 blame game. And a recent article in the Charlotte Observer brings a whole litany of complaints, finger pointing, and disappointed drivers. So lets just list all of the complaints.

First, the section of I-485 from NC 16 to I-77 and NC 115 could end up opening two years behind its Spring 2007 original planned opening date.

So what went wrong? We've covered a few of them here at the blog.

The contractor Virginia Beach based Skanska lists their beefs:

First, when they were to begin surveying in December 2003. Not all of the land for the project had been owned by the State. The state counters with it is sometime common to have a few parcels of land not owned by the State at the start of construction. However, NCDOT does concede that the 14 parcels of land that in December 2003 were not purchased were a bit excessive.

Skanska claims that the lack of a completed right-of-way process forced them to access construction sites with more difficulty.

Other complaints from Skanska include the 62 extra days it took to move a major gas line along with five other utility relocation delays.

And finally the contractor contends that they did not receive plans to provide access to a Target and car dealership until the last minute and that the plans they received were hand drawn.

Skanska claims that the state has caused the project to be 311 days behind schedule, and has requested slightly over $8.5 million in additional compensation. The state, however, view the causes for the delays otherwise.

NCDOT feels that the contractor could have easily worked on other sections of the nearly six mile project while waiting for the utilities to be moved. They also do not believe that the company has not accurately computed their losses.

In addition, NCDOT points to a January 22nd letter that required Skanska to rebuild the asphalt base on the I-485/I-77 interchange ramps because it was too thin.

But the state does admit causing 138 days in delays.

Now onto the final segment of the loop. (I-77 to I-85 near Concord/University)

It still appears that the highway will not see any construction until 2015. It appears that a preliminary opening date is 2018. (Ten years from now). Considering the various funding, procedural, and construction delays, I'm willing to go out on a limb and say that it'll be 2021 before I-485 is officially done.

Now there is one ray of hope for completing I-485. Barry moose, who is the NCDOT engineer that oversees the Charlotte area, says that if the state can find the extra money to build the highway, construction could begin in 2011.

However, he didn't guarantee that if that would happen there would be no procedural or construction delays with it either.

Story: Charlotte Observer

Comments

Popular posts from this blog

Former California State Route 41 past Bates Station

When California State Route 41 was commissioned during August 1934 it was aligned along the then existing Fresno-Yosemite Road north of the San Joaquin River.  Within the Sierra Nevada foothills of Madera County, the original highway alignment ran past Bates Station via what is now Madera County Road 209, part of eastern Road 406 and Road 207.   Bates Station was a stage station plotted during the early 1880s at what was the intersection of the Coarsegold Road and Stockton-Los Angeles Road.   The modern alignment bypassing Bates Station to the east would be reopened to traffic during late 1939.   Part 1; the history of California State Route 41 past Bates Station Bates Station was featured as one of the many 1875-1899 Madera County era towns in the May 21, 1968, Madera Tribune .  Post Office Service at Bates Station is noted to have been established on November 23, 1883 and ran continuously until October 31, 1903.  The postal name was sourced...

Abandoned US Route 40 in the Truckee River Canyon

Within the Truckee River Canyon in the Sierra Nevada range numerous abandoned portions of US Route 40 can be found alongside modern Interstate 80.   This segment of highway was opened during 1926 as a bypass of the Dog Valley Grade which carried the early North Lincoln Highway and Victory Highway. The corridor of the Truckee River Canyon State Highway would be assigned as US Route 40 when the US Route System was commissioned during November 1926. During 1958 the segment of Interstate 80 between Boca, California and the Nevada state line was complete. When Interstate 80 opened east of Boca numerous obsolete portions of US Route 40 were abandoned. Some of these abandoned segments have been incorporated into the Tahoe-Pyramid Trail.  Part 1; the history of US Route 40 in the Truckee River Canyon The Truckee River Canyon for centuries has been an established corridor of travel known to native tribes crossing the Sierra Nevada range.  The first documented wagon crossi...

The William Flinn (not Flynn) Highway - Pittsburgh's Misspelled Street

For decades if you traveled along PA Route 8 in Pittsburgh's North Hills suburbs, you would have noticed signs that read "William Flynn Highway" at every intersection.  Even today, many businesses and residences have their addresses listed as XXXX William Flynn Highway.  However, it's not William Flynn Highway, it is William FLINN Highway - and the gentleman who it is named for has a long and storied past in Pittsburgh's infrastructure history. William Flinn was born in England in 1851; however later that year, his family emigrated to the United States and would settle in Pittsburgh.  A 10-year-old school dropout, Flinn grew interested in politics and would join the Allegheny County Republican Party in 1877 as a ward commissioner and a seat on the Board of Fire Commissioners.  Flinn would serve in the Pennsylvania State House of Representatives and Senate from 1877 to 1902. (1) Flinn along with James J. Booth would found the Booth and Flinn construction firm ...