Skip to main content

There's work being done on the Mon-Fayette Expressway in West Virginia

The long-awaited final piece of the puzzle for the Mason-Dixon stretch of the Mon-Fayette Expressway is falling into place with awarding and start of construction of the final contract of the West Virginia portion of the Mon-Fayette Expressway.

When finished, the entire West Virginia portion of the Interstate 68-to-Pittsburgh highway will be complete and opened to traffic.

The contract which will include the freeway's tie in to Interstate 68 along with a total rebuild of Exit 10 on I-68 - was won by Kokosing Construction of Fredericktown, OH. The contract is funded by the 2009 American recovery and Reinvestment Act. The contract's value? Just over $11.6 million.

The contract was awarded on June 24th - construction began on July 6th. A temporary four month closure of Bowers Lane marked the start of new construction.

Kokosing is also building another piece of WV 43 just north of Interstate 68 - a nearly $23 million contract (won in December 2008) for roadwork that is just north of Interstate 68.

The plan is to have both projects completed and the freeway opened to traffic by the end of 2010. When completed, Pennsylvania will open to traffic two miles of highway from the Gans Road Interchange meeting WV 43 at the State Line.

Story:
Mon-Fayette Expressway moves closer to Cheat ---The Dominion Post

Comments

Anonymous said…
It's about time.
Anonymous said…
This is great. Commerce between Morgantown and Uniontown will improve drastically.
Anonymous said…
yes it is about time. hopefully they will build the rest of this road from 51 and also finish the southern beltway. Glad to hear west virginia is moving forward!!!

Popular posts from this blog

Memphis & Arkansas Bridge (Memphis, TN)

  Like the expansion of the railroads the previous century, the modernization of the country’s highway infrastructure in the early and mid 20th Century required the construction of new landmark bridges along the lower Mississippi River (and nation-wide for that matter) that would facilitate the expected growth in overall traffic demand in ensuing decades. While this new movement had been anticipated to some extent in the Memphis area with the design of the Harahan Bridge, neither it nor its neighbor the older Frisco Bridge were capable of accommodating the sharp rise in the popularity and demand of the automobile as a mode of cross-river transportation during the Great Depression. As was the case 30 years prior, the solution in the 1940s was to construct a new bridge in the same general location as its predecessors, only this time the bridge would be the first built exclusively for vehicle traffic. This bridge, the Memphis & Arkansas Bridge, was completed in 1949 and was the third

Old River Lock & Control Structure (Lettsworth, LA)

  The Old River Control Structure (ORCS) and its connecting satellite facilities combine to form one of the most impressive flood control complexes in North America. Located along the west bank of the Mississippi River near the confluence with the Red River and Atchafalaya River nearby, this structure system was fundamentally made possible by the Flood Control Act of 1928 that was passed by the United States Congress in the aftermath of the Great Mississippi River Flood of 1927 however a second, less obvious motivation influenced the construction here. The Mississippi River’s channel has gradually elongated and meandered in the area over the centuries, creating new oxbows and sandbars that made navigation of the river challenging and time-consuming through the steamboat era of the 1800s. This treacherous area of the river known as “Turnbull’s Bend” was where the mouth of the Red River was located that the upriver end of the bend and the Atchafalaya River, then effectively an outflow

California State Route 203 the proposed Minaret Summit Highway

California State Route 203 is an approximately nine-mile State Highway located near Mammoth Lakes in the Sierra Nevada Mountains of Mono County.  California State Route 203 as presently configured begins at US Route 395, passes through Mammoth Lakes and terminates at the Madera County line at Minaret Summit.  What is now California State Route 203 was added to the State Highway System in 1933 as Legislative Route Number 112.  The original Mammoth Lakes State Highway ended at Lake Mary near the site of Old Mammoth and was renumbered to California State Route 203 in 1964.  The modern alignment of the highway to Minaret Summit was adopted during 1967.   The corridor of Minaret Summit and Mammoth Pass have been subject to numerous proposed Trans-Sierra Highways.  The first corridor was proposed over Mammoth Pass following a Southern Pacific Railroad survey in 1901.  In 1931 a corridor between the Minarets Wilderness and High Sierra Peaks Wilderness was reserved by the Forest Service for po