NCTA continues to look at tolling I-140/US 17 to pay for Cape Fear Skyway

The NCTA is looking at the possibility of tolling part of or all of the US 17/I-140 Wilmington Bypass as a way of generating additional funds for the Cape Fear Skyway.

Currently, the projected revenue from the 9.5 mile toll road would only pay for half the cost of the $1.0 - $1.5 billion project. As a result, that would require a minimum of $49.2 million per year gap funding paid for out of North Carolina's general budget for 40 years.

Tolling the entire bypass (when completed) could possibly reduce the gap funding at an $11 million per year rate. In fact, the NCTA estimates that in a 40 year period tolls on the Wilmington Bypass would generate more revenue than the Skyway. $2.4 billion over 40 years compared to $1.5 billion over 40 years for the Skyway.

Of course, because the Wilmington Bypass has been funded with federal tax dollars, it would need to get approval from not only the state legislature (which has to approve all toll projects) but from the federal government as well.

Story:
Tolls on the table for Skyway Project ---Wilmington Star-News

Commentary:
The NCTA has been hinting at this proposal for quite some time. In fact, nearly 18 months ago the Leland Town Council passed a resolution opposing any tolls on the Wilmington Bypass. The motion was passed unanimously.

As much as the Cape Fear Skyway is needed and as much as I applaud any suggestion to reduce overall costs to taxpayers, this idea isn't going to work. Tolling existing free roads to pay for future toll roads will not sit well with Wilmington residents, tourists, and citizens throughout North Carolina. The state is more likely to gain support for a transportation or road gasoline or even another increase in the sales tax than they would for tolling a previously 'free' highway just to build another toll road. That's not counting they would have to get approval from the FHWA and Congress.

My guess is that the NCTA will try to spin the Wilmington Bypass and Cape Fear Skyway as one total project - and looking at it on a map - yes you could. But the reality is, they aren't.

And hypothetically, if this proposal is allowed to happen - this just gives the NCTA the green light to toll other existing roads just to pay for the construction of another toll road.

Comments

Popular posts from this blog

The Relief Route That Wasn't: The Never Built I-70 Bypass in the Mid-Mon Valley

In June 1963, a small blurb in the Pittsburgh Post-Gazette read that The Westmoreland Engineering Company was awarded a $24,060 bid to study the proposed construction of Interstate 70 in Westmoreland and Washington Counties.  The study was to see what the construction and right-of-way costs "...to modernize the existing highway to Interstate requirements within eight months." (1)  This small, non-attributed, three paragraph article came less than a decade after the completion of a four lane highway that linked the Mid-Mon Valley to the Pennsylvania Turnpike. This would be the start of a 15 year process to upgrade and improve Interstate 70 - a process that ultimately never produced a single foot of new highway.

This is the story, albeit brief, of the I-70 that never came about.

Background:
What is now known as Interstate70 from Washington to New Stanton began as a connecting highway for the region to the Pennsylvania Turnpike.  Known as the "Express Highway", construct…

The Many Failed Plans of Pittsburgh's Wabash Bridge and Tunnel

The December 27, 2004 opening of the Wabash Tunnel ended over 70 years of proposals and speculation for the use of the over 100 year old facility.  The tunnel, which is now a reversible roadway that is an alternative route for rush hour traffic, saw many failed plans during the 20th Century.  These plans included options for mass transit, converted and new bridges for vehicles, and other forms of transportation.

Brief History:
Constructed in 1902-04, the Wabash Bridge and Tunnel was planned and financed by rail mogul, Jay Gould.  Gould began his "Battle of the Wabash" with the established railroads of the city in 1890.  He would finally emerge victorious, but during that struggle, Gould would see many setbacks that would eventually result in the railroad's bankruptcy in 1908.  On October 19, 1903, when the two ends of the bridge were to be joined together over the Monongahela River, the 109' bridge collapsed; killing ten men.  Construction would resume four days later …

A look at Pittsburgh's Saw Mill Run Boulevard

Saw Mill Run Boulevard - Pennsylvania State Route 51 - runs through the narrow Saw Mill Run Valley.  It begins at the intersection of Clairton Road and Provost Road at the City of Pittsburgh Line with Brentwood.  It ends at the West End Circle at the entrance to the West End Bridge.  A four lane highway for its the entire length, Saw Mill Run Boulevard consists of interchanges at the South Portal of the Liberty Tubes and with the Parkway West.  It is an expressway from the Parkway to the West End Circle (West End Bypass).  One of the most well known traffic tie-ups in the Pittsburgh area occurs between Maytide Street and PA 88 (Library Road) which is simply known as 'Maytide and 88.'

History:
Saw Mill Run Boulevard was part of the 1928 Allegheny County 'City Beautiful' bond issue.  The bonds resulted in the creation of Saw Mill Run, Ohio River, Allegheny River and Mosside Boulevards. (1)   After the completion of the Liberty Tunnels in 1924, Downtown Pittsburgh was offic…