Perdue offers I-485 financing plan, but many questions need to be answered first

Earlier today, Governor Perdue announced her plan to complete the Interstate 485 loop in the next five years. The plan is something called a design-build-finance plan, and it has yet to be used within North Carolina. However, there are a number of hurdles and loopholes within the plan

The term 'design-build' is familiar within North Carolina transportation projects. Design-build projects are where the builder also designs the overall project- often while the project is ongoing. One of North Carolina's first design-build projects was the Interstate 85 widening between miles 40-48.

'Design-build-finance' is where the contractor pays for some or all of the construction and then gets reimbursed by the state within a specified period of time. This method has been used elsewhere in the country including an Interstate 69 reconstruction project in Michigan.

The projected cost to complete the remaining five miles of I-485 is now roughly $340 million.

Under this plan, construction for I-485 will start next year and be completed by 2015. Plus, the governor's office emphasizes that money will not come from or delay other projects.

Sounds too good to be true right? The contractor pays for some of the construction, gets paid back by the state, no other projects get delayed.

Well, I need that Lee Corso photo again...because "Not so fast, my friend!"

First, the financing method. The contractor would pay $50 million of the $340 million to construct the highway. Well, first you have to find a construction firm that has $50 million in cash to finance the highway. And with troubles NCDOT has had with various construction companies over the past decade, that's not a guarantee.

Adam Froehlig, in a post to a national transportation forum, notes that this approach was tried for Minnesota's Crosstown Commons project but no construction firm placed a bid.

The $50 million that the construction company puts down for the highway would be paid back by the state over a 10 year period. Questions come from that too. What will the interest rate be...will the money owed to the construction company, somewhere between $5-6 million a year, impact financing other projects? With the state and the DOT in the red, will the state be able to pay it back over that period?

If the contractor is only paying $50 million or 14.7% of the costs, where is the other money coming from? The Governor's office says that no other project will be delayed. Well, according to the Charlotte Observer, the DOT's chief financial officer, Mark L. Foster, admits that the DOT is 'prioritizing' projects statewide, including I-485. If this is the case, then aren't other projects going to be delayed? Plus, when the missing five miles cost only $220 to construct - the state said they had no money to complete it. Now, they need to come up with $290 million - that's $70 million more than the original estimated cost - and suddenly NCDOT has the money.

The highway that most likely will be delayed is Interstate 295 in Fayetteville, which has the whipping boy for every other city in the state who has seen delays in their planned freeway loops.

Personally, I'd like to see where this $290 million will come from. Will the controversial equity formula be repealed? Will they try to sneak in tolls? Something just doesn't add up here.

There are other hurdles for the highway - specifically environmental concerns. Charlotte has had a growing ozone (ground level) issue and has been under the careful eye of the US Environmental Protection Agency. In fact, highway funding for Charlotte has been threatened to be cutoff if the metro area didn't improve air quality. Groups like the Southern Environmental Law Center will be certain to keep a close eye on this process.

Now what if this works?

Well, as the economy improves, more construction companies will be able to assist in financing similar projects. This could possibly speed up delayed projects and also eliminate future projects becoming toll roads.

So there could be a new opportunity for the future of North Carolina highways. However, this is a big test, and a lot of interested parties will be keeping their eye on how the final five miles of Interstate 485 eventually gets built. There is a lot riding on this project - not only politically for Governor Perdue - but on how other highway projects in North Carolina are built short and long term. It will be an interesting few months and years to see how this all unfolds.

Story Links:
I-485 plan: Tap builder cash ---Charlotte Observer
Gov. says work to finish I-485 will start in 2010 ---WBTV-TV
Governor says I-485 will be completed in five years ---WCNC-TV
Perdue unveils plan to complete Interstate 485 ---News14Carolina

Comments

This comment has been removed by a blog administrator.
Anonymous said…
This comment has been removed by a blog administrator.

Popular posts from this blog

Paper Highways: The Unbuilt New Orleans Bypass (Proposed I-410)

  There are many examples around the United States of proposed freeway corridors in urban areas that never saw the light of day for one reason or another. They all fall somewhere in between the little-known and the infamous and from the mundane to the spectacular. One of the more obscure and interesting examples of such a project is the short-lived idea to construct a southern beltway for the New Orleans metropolitan area in the 1960s and 70s. Greater New Orleans and its surrounding area grew rapidly in the years after World War II, as suburban sprawl encroached on the historically rural downriver parishes around the city. In response to the development of the region’s Westbank and the emergence of communities in St. Charles and St. John the Baptist Parishes as viable suburban communities during this period, regional planners began to consider concepts for new infrastructure projects to serve this growing population.  The idea for a circular freeway around the southern perimeter of t

Hernando de Soto Bridge (Memphis, TN)

The newest of the bridges that span the lower Mississippi River at Memphis, the Hernando de Soto Bridge was completed in 1973 and carries Interstate 40 between downtown Memphis and West Memphis, AR. The bridge’s signature M-shaped superstructure makes it an instantly recognizable landmark in the city and one of the most visually unique bridges on the Mississippi River. As early as 1953, Memphis city planners recommended the construction of a second highway bridge across the Mississippi River to connect the city with West Memphis, AR. The Memphis & Arkansas Bridge had been completed only four years earlier a couple miles downriver from downtown, however it was expected that long-term growth in the metro area would warrant the construction of an additional bridge, the fourth crossing of the Mississippi River to be built at Memphis, in the not-too-distant future. Unlike the previous three Mississippi River bridges to be built the city, the location chosen for this bridge was about two

Memphis & Arkansas Bridge (Memphis, TN)

  Like the expansion of the railroads the previous century, the modernization of the country’s highway infrastructure in the early and mid 20th Century required the construction of new landmark bridges along the lower Mississippi River (and nation-wide for that matter) that would facilitate the expected growth in overall traffic demand in ensuing decades. While this new movement had been anticipated to some extent in the Memphis area with the design of the Harahan Bridge, neither it nor its neighbor the older Frisco Bridge were capable of accommodating the sharp rise in the popularity and demand of the automobile as a mode of cross-river transportation during the Great Depression. As was the case 30 years prior, the solution in the 1940s was to construct a new bridge in the same general location as its predecessors, only this time the bridge would be the first built exclusively for vehicle traffic. This bridge, the Memphis & Arkansas Bridge, was completed in 1949 and was the third