Skip to main content

Final Progress Report on I-74/US 311 Freeway for 2009

Made my last trip of 2009 to check out progress on the construction of the I-74/US 311 freeway from High Point to Randleman during midday today (12/12). Based on the NCDOT's Construction Progress Report there hasn't been much going on along the Business 85 to Cedar Square Road segment the last two months as far as percentage complete goes, now up to about 81% complete at the end of November compared to 78% in September. There has been, however, some noticeable progress on the two remaining bridge projects as well on some of the roadway itself.

Going West to East (or North to South depending on which route you prefer) the first stop is the Baker Road bridge. Work has been completed on the bridge decks as you can see here (yes, they were working on Saturday, making up for bad weather maybe):
The bridge is capable of supporting traffic, as the truck driving across it shows here:
You can see they still have to connect the bridge to the pre-exisiting alignment of Baker Road and build the bridge walls and railings before being open to traffic. This could happen before the end of the year if the weather cooperates.
They are still working on getting the road down to grade south of the bridge and will start north when the bridge is opened and the temporary roadway to the north can be demolished.

Jackson Lake Bridge. Not much progress here west of the bridge, as you can see they still don't have a westbound roadway here, still just piles of dirt:
The roadway to the east toward the Kersey Valley bridge, however, is basically complete and can support contractor traffic as you can see below:
Kersey Valley Road area. Again little progress here. Some more excavation has been done to the roadway west of the bridge:
Notice less construction equipment and machinery present than last month by the graded slopes going eastbound. The view of the roadway between Kersey Valley and I-85 shows more work is needed:
Most of the depressions are filled with water which, due to today's cold temperatures, had turned to ice. They are going to have to wait until this dries up to proceed.

The I-85 interchange. Some progress here, if you look behind the flyover bridge (the farthest) you'll notice the top of an overhead sign structure for the I-85 exit that has been put up. A cantilevered overhead sign structure was also put up just north of the NC 62 bridge.
Another photo of the same area showing progress around the interchange offramp, it appears more grading has been done down toward the future eastbound roadway. And if you didn't notice before, the west wall to the flyover bridge has been completed:
Tuttle Road. There has been more progress in placing guardrails along this section. Looking west you can see there are now guardrails on both directions of the highway:
There is also now guardrail looking east/southbound:
It appears that there is an asphalt layer capable of carrying traffic now from just east of the I-85 interchange heading east almost to Cedar Square Road, with a few exceptions. Notice the truck below is heading the wrong way, but demonstrates it is possible to get to near Cedar Square Road (that would be easiest way off the freeway).
A closer look at the Tuttle Road bridge heading east:
The Cedar Square Road bridge and Interchange. Most of the progress in the last month has been made here. First, the bridge has been opened:
To the right is the old road alignment which will be access to Poole Road. (The connection has been made but the road was blocked by road closed signs, this wasn't preventing locals from making there way around them to access Cedar Square). Now crossing the bridge:
The bridge has 3 lanes, the center reserved for those wanting to make a left turn onto I-74 East, Which occurs just before where this photo was taken looking at the new intersection with US 311:
Second, progress on the on and offramps. For eastbound traffic these are opposite each other while the westbound ramps are on the south side of Cedar Square. Here's the progress being made on the westbound on/off ramps:
Here's a look on the progress of building the eastbound off ramp:
They still need to remove the old alignment of Cedar Square in the freeway's path before final grading and paving can be made.
Meanwhile all the construction equipment is at the end of the current road awaiting construction on the second part to complete the freeway to US 220:
US 311. Some additional clearing in the construction area, and the start of one of the on or offramps, but little else:
US 220. Some progress here in the appearance of a second center support in the median for the other flyover ramp:
Here's progress on the first flyover support, plus clearing on the northbound side:
The wider view of the construction area, heading northbound:
Progress on the future I-74 West Flyover ramp:
They are working also on expanding US 220 to 3 lanes (seen beyond the barrier) between Pineview Street and the existing US 311 exit:
Notice the polls for a new exit sign. These also appear elsewhere along US 220, not just in the I-74 construction area implying another project installing new exit signs, hopefully before the I-74 project is finished and with I-73 mileage based numbers.

My next trip will be after they open the new rest areas/visitor's centers near Seagrove on I-73/74 sometime in January (current completion date is 1/21/10). I'll let everyone know when they are open, in case anyone else wants to come along and tour them.

Comments

Popular posts from this blog

Check the box: Interstate 495 to 87 conversion administratively approved

The American Association of State Highway and Transportation Officials have recently approved North Carolina's application to remove the short-lived Interstate 495 and future I-495 from Raleigh to Rocky Mount.  This administrative move most likely will result in North Carolina signing Interstate 87 and Future I-87 on the entire corridor in the near future.

Approved in 2013, Interstate 495 was first signed in 2014 along US 64 from Interstate 440 in Raleigh to Interstate 540 in Knightdale.  The remaining segment of highway to Rocky Mount was signed as Future Interstate 495.  However, in 2016, North Carolina's congressional legislators were able to get language in the 2015 FAST ACT designating the US 64/US 13/US 17 corridor from Raleigh to Norfolk as an Interstate.  In 2016, the FHWA and AASHTO designated this entire corridor (including the existing Interstate and Future 495) as Interstate 87.  (NCDOT had applied for Interstate 89 along this route.)

It is currently unknown when t…

The story on how the unbuilt US 40 Expressway in Brownsville took 40 years to complete.

For nearly four decades, the four lane US 40 just east of Brownsville came to an abrupt end - shown in the photo above - at Grindstone Road in Redstone Township.   In the late 1960s, what was then the Pennsylvania Division of Highways (PennDOH) extended a new four lane alignment of US 40 eastwards from Broadway Street slightly over one mile to Grindstone Road where an incomplete diamond interchange was built.  Earlier in the decade, PennDOH had built a four lane US 40 in Washington County into Brownsville complete with a new crossing over the Monongahela River known as the Lane Bane Bridge.  This new highway and bridge allowed US 40 to bypass the older Intercounty Bridge and downtown Brownsville. 

After this new highway opened, nothing would happen to it for nearly forty years.  US 40 traffic would use the ramps for this planned diamond interchange and then jog on Grindstone Road briefly before continuing towards Uniontown on the original National Road. 
What is unknown (at least to…

A quick Illinois and Wisconsin Road Trip

Recently, I was in the Chicago area and was able to explore the area north of Chicago and Wisconsin in my downtime.  I pretty much did a loop that consisted of Interstate 94, Interstate 43, US 12, Illinois Route 120, and Illinois Route 60.  It was my first real time exploring the area.  I ended up gaining an additional five counties on the trip bringing my total to just short of 1100, 1099 to be exact.

For the entire flickr set of photos for this trip, please head here.

Just prior to entering Wisconsin on Interstate 94, you will come across this sign.  Out of nowhere, Interstate 41 appears.  And if you aren't hip to changes on your map, Interstate 41 is a rather recently new interstate that runs from Green Bay to just about a mile inside the Illinois border.  Interstate 41 is an upgraded routing of the US 41 freeway that runs from Milwaukee to Green Bay; however, it was added along Interstate's 894 and 94 South of Milwaukee to where US 41 leaves I-94.  In fact, throughout the…