Final Progress Report on I-74/US 311 Freeway for 2009

Made my last trip of 2009 to check out progress on the construction of the I-74/US 311 freeway from High Point to Randleman during midday today (12/12). Based on the NCDOT's Construction Progress Report there hasn't been much going on along the Business 85 to Cedar Square Road segment the last two months as far as percentage complete goes, now up to about 81% complete at the end of November compared to 78% in September. There has been, however, some noticeable progress on the two remaining bridge projects as well on some of the roadway itself.

Going West to East (or North to South depending on which route you prefer) the first stop is the Baker Road bridge. Work has been completed on the bridge decks as you can see here (yes, they were working on Saturday, making up for bad weather maybe):
The bridge is capable of supporting traffic, as the truck driving across it shows here:
You can see they still have to connect the bridge to the pre-exisiting alignment of Baker Road and build the bridge walls and railings before being open to traffic. This could happen before the end of the year if the weather cooperates.
They are still working on getting the road down to grade south of the bridge and will start north when the bridge is opened and the temporary roadway to the north can be demolished.

Jackson Lake Bridge. Not much progress here west of the bridge, as you can see they still don't have a westbound roadway here, still just piles of dirt:
The roadway to the east toward the Kersey Valley bridge, however, is basically complete and can support contractor traffic as you can see below:
Kersey Valley Road area. Again little progress here. Some more excavation has been done to the roadway west of the bridge:
Notice less construction equipment and machinery present than last month by the graded slopes going eastbound. The view of the roadway between Kersey Valley and I-85 shows more work is needed:
Most of the depressions are filled with water which, due to today's cold temperatures, had turned to ice. They are going to have to wait until this dries up to proceed.

The I-85 interchange. Some progress here, if you look behind the flyover bridge (the farthest) you'll notice the top of an overhead sign structure for the I-85 exit that has been put up. A cantilevered overhead sign structure was also put up just north of the NC 62 bridge.
Another photo of the same area showing progress around the interchange offramp, it appears more grading has been done down toward the future eastbound roadway. And if you didn't notice before, the west wall to the flyover bridge has been completed:
Tuttle Road. There has been more progress in placing guardrails along this section. Looking west you can see there are now guardrails on both directions of the highway:
There is also now guardrail looking east/southbound:
It appears that there is an asphalt layer capable of carrying traffic now from just east of the I-85 interchange heading east almost to Cedar Square Road, with a few exceptions. Notice the truck below is heading the wrong way, but demonstrates it is possible to get to near Cedar Square Road (that would be easiest way off the freeway).
A closer look at the Tuttle Road bridge heading east:
The Cedar Square Road bridge and Interchange. Most of the progress in the last month has been made here. First, the bridge has been opened:
To the right is the old road alignment which will be access to Poole Road. (The connection has been made but the road was blocked by road closed signs, this wasn't preventing locals from making there way around them to access Cedar Square). Now crossing the bridge:
The bridge has 3 lanes, the center reserved for those wanting to make a left turn onto I-74 East, Which occurs just before where this photo was taken looking at the new intersection with US 311:
Second, progress on the on and offramps. For eastbound traffic these are opposite each other while the westbound ramps are on the south side of Cedar Square. Here's the progress being made on the westbound on/off ramps:
Here's a look on the progress of building the eastbound off ramp:
They still need to remove the old alignment of Cedar Square in the freeway's path before final grading and paving can be made.
Meanwhile all the construction equipment is at the end of the current road awaiting construction on the second part to complete the freeway to US 220:
US 311. Some additional clearing in the construction area, and the start of one of the on or offramps, but little else:
US 220. Some progress here in the appearance of a second center support in the median for the other flyover ramp:
Here's progress on the first flyover support, plus clearing on the northbound side:
The wider view of the construction area, heading northbound:
Progress on the future I-74 West Flyover ramp:
They are working also on expanding US 220 to 3 lanes (seen beyond the barrier) between Pineview Street and the existing US 311 exit:
Notice the polls for a new exit sign. These also appear elsewhere along US 220, not just in the I-74 construction area implying another project installing new exit signs, hopefully before the I-74 project is finished and with I-73 mileage based numbers.

My next trip will be after they open the new rest areas/visitor's centers near Seagrove on I-73/74 sometime in January (current completion date is 1/21/10). I'll let everyone know when they are open, in case anyone else wants to come along and tour them.

Comments

Popular posts from this blog

The Relief Route That Wasn't: The Never Built I-70 Bypass in the Mid-Mon Valley

In June 1963, a small blurb in the Pittsburgh Post-Gazette read that The Westmoreland Engineering Company was awarded a $24,060 bid to study the proposed construction of Interstate 70 in Westmoreland and Washington Counties.  The study was to see what the construction and right-of-way costs "...to modernize the existing highway to Interstate requirements within eight months." (1)  This small, non-attributed, three paragraph article came less than a decade after the completion of a four lane highway that linked the Mid-Mon Valley to the Pennsylvania Turnpike. This would be the start of a 15 year process to upgrade and improve Interstate 70 - a process that ultimately never produced a single foot of new highway.

This is the story, albeit brief, of the I-70 that never came about.

Background:
What is now known as Interstate70 from Washington to New Stanton began as a connecting highway for the region to the Pennsylvania Turnpike.  Known as the "Express Highway", construct…

The Many Failed Plans of Pittsburgh's Wabash Bridge and Tunnel

The December 27, 2004 opening of the Wabash Tunnel ended over 70 years of proposals and speculation for the use of the over 100 year old facility.  The tunnel, which is now a reversible roadway that is an alternative route for rush hour traffic, saw many failed plans during the 20th Century.  These plans included options for mass transit, converted and new bridges for vehicles, and other forms of transportation.

Brief History:
Constructed in 1902-04, the Wabash Bridge and Tunnel was planned and financed by rail mogul, Jay Gould.  Gould began his "Battle of the Wabash" with the established railroads of the city in 1890.  He would finally emerge victorious, but during that struggle, Gould would see many setbacks that would eventually result in the railroad's bankruptcy in 1908.  On October 19, 1903, when the two ends of the bridge were to be joined together over the Monongahela River, the 109' bridge collapsed; killing ten men.  Construction would resume four days later …

A look at Pittsburgh's Saw Mill Run Boulevard

Saw Mill Run Boulevard - Pennsylvania State Route 51 - runs through the narrow Saw Mill Run Valley.  It begins at the intersection of Clairton Road and Provost Road at the City of Pittsburgh Line with Brentwood.  It ends at the West End Circle at the entrance to the West End Bridge.  A four lane highway for its the entire length, Saw Mill Run Boulevard consists of interchanges at the South Portal of the Liberty Tubes and with the Parkway West.  It is an expressway from the Parkway to the West End Circle (West End Bypass).  One of the most well known traffic tie-ups in the Pittsburgh area occurs between Maytide Street and PA 88 (Library Road) which is simply known as 'Maytide and 88.'

History:
Saw Mill Run Boulevard was part of the 1928 Allegheny County 'City Beautiful' bond issue.  The bonds resulted in the creation of Saw Mill Run, Ohio River, Allegheny River and Mosside Boulevards. (1)   After the completion of the Liberty Tunnels in 1924, Downtown Pittsburgh was offic…