April I-74/US 311 Freeway Progress Report

Apparently not having seen enough construction on Saturday, I traveled to Winston-Salem and back to check on the progress of building the US 74/US 311 freeways near High Point.

1. High Point 'East Belt'
A. Open Portion
Why did I start in Winston-Salem. Part of the contract for building the 'East Belt' portion of I-74 (from now former Business 311 to I-85) calls for updating signs to include I-74 (the plans indicated full interstate, but it may now be Future) and the placing of I-74 mile markers along the already opened portion of the road to Business 85. I was checking to see if there were any indications this was happening, which would mean the route is closer to opening than NCDOT has announced, by the end of the year. The only change on the existing road I could find though were to the overhead signs at the now former Business 311 interchange heading east (Exit 65). Both signs, except for the exit tab, had been removed:
The sign on the left read 'To NC 68'. It turns out though that these signs were blown down a tornado that passed over a week or so before. Thus NCDOT will have to decide to replace them as they were or replace them by updated signs, such as an East I-74/South US 311 sign with control cities at some future point. The Exit 65 sign before this one, since the removal above was not due to NCDOT, at 1 mile had not been replaced and still referred to Business 311.

B. Under Construction Portion from Business to Interstate 85
Baker Road Bridge-As my last post indicated the bridge had been opened but there was no progress on removing the temporary highway to the north. Well, there has been some progress in the last month:
The pavement has been removed and digging has begun to bring the road down to grade, which has been done just to the north of the bridge. There has been substantial progress south of the bridge, where much of the grading and landscaping needed has been done:
The paved portion where the road curves continues eastbound to the Jackson Lake Road bridge.
Looking from Jackson Lake Road, most of the dirt from the former hill in the westbound lanes has been pushed up the embankment on the right and is being prepared for final landscaping. Looking eastbound toward Kersey Valley Road, it appears most of the work is complete:
Guardrails and drain covers are still needed, but most of the landscaping is done. Here is how the Kersey Valley Road bridge looks from the south:
The roadways appear graded and they have started initial paving toward I-85 along the future eastbound lanes shown on the left side of the photo in the middle. This is a better view of what progress has been made:
They've tied the new pavement on the EB I-85 ramp to the existing pavement. Landscaping though and more paving has to be completed here. The view of the I-85 bridges also shows progress in the last month:
Grading appears almost complete and the asphalt layer in the eastbound lanes continues almost to the bridges. The contractor has been closing lanes and ramps on I-85 in this area for the past 2 weeks to put new lane striping on I-85, for paving the NC 62 exit ramps, and for putting up overhead sign supports:
Whether this means the re-opening of the main I-85 lanes is imminent is not known, the NCDOT construction progress report still says this will happen in June. Work on the exit ramps continues...
The flyover ramp from I-74 East to I-85 North above looks complete, however, it doesn't appear paving has been completed on the section of the ramp from the bridge over I-85 to the flyover ramp...
Presumably, guardrails will be added when the paving project is completed.

2. '311 Bypass' I-85 to US 220
A. First Phase portion-This part of the freeway is being built at the same time by the people doing the remaining East Belt construction. The roadbed near the I-85 interchange appears mostly complete:
Most of the work in this section over the past month seems to be concentrated on the placing of a final asphalt layer on the roads that cross the future freeway. The paving and lane striping of Tuttle Road across its bridge has been finished:
Similar work has been done along Poole Road and on Cedar Square Road. The final non-highway bridge that needed construction has been completed, as can be seen in this photo from the Poole Road bridge:
As can be seen though, little or no further work on paving the freeway has occurred either to the north or south of the bridge:
Approaching Cedar Square Road, Poole Road parallels the freeway on the right. There was progress in re-doing Poole Road where it met the former alignment of Cedar Square Road, the road now curves off to the left on a new alignment. The photo of the Cedar Square Road Bridge below is taken where Poole Road now curves toward Cedar Square:
Work has been done on grading the route where the old alignment of Cedar Square was torn down. There, has not been much work on the interchange ramps, however:
Both Cedar Square Road and current US 311 from just south of the intersection below to just north of the former Cedar Square intersection have received their final coat of asphalt:
The water tower in the background is either being replaced or augmented by a new bigger water tower further south on US 311 which has a big 'Welcome to High Point' logo on it. I suppose they hope people will see it from the new freeway.

B. Phase 2
The second phase of construction runs from Spencer Road, 1/2 mile south of Cedar Square, to US 220. This is a design-build contract where work started in late 2008. The major feature of this segment will be an interchange with current US 311 in Sophia and the interchange where I-74 will tie into I-73 (US 220) near Randleman. There is little more than clearing going on at the Sophia interchange so far:
Most of the clearing seems to have been done, seen from US 311 South, the crane indicates the start of some infrastructure construction. There are more interesting things to see on US 220:
Traveling southbound, they are now putting structures in for the I-74 bridges on the right side, the first one is mostly metal and will lead to the I-74 west lanes that are being graded in the vicinity. The second structure is mostly cement and this will take traffic from I-74 east to I-73 north:
This will be a lower bridge, the ramp to I-74 west will be a flyover and go both over US 220 and the other bridge. This requires building a large mound along northbound US 220 for the ramp to the flyover, seen below from the southbound lanes:
One can barely see the top of the future ramp when traveling along in the northbound lanes:
Here's a wider view of the construction scene as viewed going northbound on US 220:
The first phase and East-Belt construction are 86% complete as of the end of March according to NCDOT, the contractors having completed over 3 1/2% of the remaining construction during the month. At this pace the route from Business 85 to Cedar Square Road could be done by the end of July. I will return sometime in May to see if this prediction is still possible.

Comments

Anonymous said…
Signs for 311/Main St in High Point were blown down in last week's tornado. It should be interesting to see what they are replaced with.
Bob Malme said…
Thanks for the information. I have revised the comment regarding the missing Exit 65 signs in light of the new information.

Popular posts from this blog

The story on how the unbuilt US 40 Expressway in Brownsville took 40 years to complete.

For nearly four decades, the four lane US 40 just east of Brownsville came to an abrupt end - shown in the photo above - at Grindstone Road in Redstone Township.   In the late 1960s, what was then the Pennsylvania Division of Highways (PennDOH) extended a new four lane alignment of US 40 eastwards from Broadway Street slightly over one mile to Grindstone Road where an incomplete diamond interchange was built.  Earlier in the decade, PennDOH had built a four lane US 40 in Washington County into Brownsville complete with a new crossing over the Monongahela River known as the Lane Bane Bridge.  This new highway and bridge allowed US 40 to bypass the older Intercounty Bridge and downtown Brownsville. 

After this new highway opened, nothing would happen to it for nearly forty years.  US 40 traffic would use the ramps for this planned diamond interchange and then jog on Grindstone Road briefly before continuing towards Uniontown on the original National Road. 
What is unknown (at least to…

The story of the Boy Scout Ramps on Interstate 79 North in NW Pennsylvania

If you are traveling on Interstate 79 North of Pittsburgh, you may notice the remnants of a set of off and on ramps at mile 100 just north of Exit 99 (US 422).  There's a story behind these ramps.  Forty years ago, these ramps were built specifically for two Boy Scout Jamboree's that were held at Moraine State Park - 1973 and 1977.  The ramps purpose were to provide access to the north shore of Lake Arthur where the bulk of the festivities and campsite for the Jamboree were located.  (Lawrence County Memories has a great write up and map of the festivities on its site.)

Not long after the Jamboree ended the ramps were abandoned.  There are still remnants of the Boy Scout Ramps today.



Above: Sattelite view of the Boy Scout Jamboree Ramps. 
Below: A view of the ramps from I-79 South.



The google street view image above gives a view along West Park Road of where the set of ramps intersected the highway.  The ramps provided direct access to North Shore Drive (which is the right tur…

The few clues of the Northern Durham Parkway

Sometimes when you look through a box of maps for the first time in five years, you come across something you may have easily over looked.  Such was the case when I found a 2004 (so rather recent) map of Raleigh.  This map was made by the Dolph Map Company for WakeMed.  In the Northwestern corner of Wake County, there were two items to the map showing roads that are still not in existence 13 years later.

The road is the Northern Durham Parkway - this is a proposed 19 mile highway from US 501 north of Durham to the Raleigh-Durham International Airport.  The first proposals for this highway date back to 1967 when Eno Drive-Gorman Road was listed on the Durham Area Thoroughfare Plan. (1)  Other proposals called the highway the Northwest and Northeast Durham Loop. (2)  The route would serve as a northern and eastern bypass of Durham almost serving as a near loop.  The route was fought vigorously for three decades by the Eno River Association citing concerns for the the Eno River, nearby n…