Skip to main content

April I-74/US 311 Freeway Progress Report

Apparently not having seen enough construction on Saturday, I traveled to Winston-Salem and back to check on the progress of building the US 74/US 311 freeways near High Point.

1. High Point 'East Belt'
A. Open Portion
Why did I start in Winston-Salem. Part of the contract for building the 'East Belt' portion of I-74 (from now former Business 311 to I-85) calls for updating signs to include I-74 (the plans indicated full interstate, but it may now be Future) and the placing of I-74 mile markers along the already opened portion of the road to Business 85. I was checking to see if there were any indications this was happening, which would mean the route is closer to opening than NCDOT has announced, by the end of the year. The only change on the existing road I could find though were to the overhead signs at the now former Business 311 interchange heading east (Exit 65). Both signs, except for the exit tab, had been removed:
The sign on the left read 'To NC 68'. It turns out though that these signs were blown down a tornado that passed over a week or so before. Thus NCDOT will have to decide to replace them as they were or replace them by updated signs, such as an East I-74/South US 311 sign with control cities at some future point. The Exit 65 sign before this one, since the removal above was not due to NCDOT, at 1 mile had not been replaced and still referred to Business 311.

B. Under Construction Portion from Business to Interstate 85
Baker Road Bridge-As my last post indicated the bridge had been opened but there was no progress on removing the temporary highway to the north. Well, there has been some progress in the last month:
The pavement has been removed and digging has begun to bring the road down to grade, which has been done just to the north of the bridge. There has been substantial progress south of the bridge, where much of the grading and landscaping needed has been done:
The paved portion where the road curves continues eastbound to the Jackson Lake Road bridge.
Looking from Jackson Lake Road, most of the dirt from the former hill in the westbound lanes has been pushed up the embankment on the right and is being prepared for final landscaping. Looking eastbound toward Kersey Valley Road, it appears most of the work is complete:
Guardrails and drain covers are still needed, but most of the landscaping is done. Here is how the Kersey Valley Road bridge looks from the south:
The roadways appear graded and they have started initial paving toward I-85 along the future eastbound lanes shown on the left side of the photo in the middle. This is a better view of what progress has been made:
They've tied the new pavement on the EB I-85 ramp to the existing pavement. Landscaping though and more paving has to be completed here. The view of the I-85 bridges also shows progress in the last month:
Grading appears almost complete and the asphalt layer in the eastbound lanes continues almost to the bridges. The contractor has been closing lanes and ramps on I-85 in this area for the past 2 weeks to put new lane striping on I-85, for paving the NC 62 exit ramps, and for putting up overhead sign supports:
Whether this means the re-opening of the main I-85 lanes is imminent is not known, the NCDOT construction progress report still says this will happen in June. Work on the exit ramps continues...
The flyover ramp from I-74 East to I-85 North above looks complete, however, it doesn't appear paving has been completed on the section of the ramp from the bridge over I-85 to the flyover ramp...
Presumably, guardrails will be added when the paving project is completed.

2. '311 Bypass' I-85 to US 220
A. First Phase portion-This part of the freeway is being built at the same time by the people doing the remaining East Belt construction. The roadbed near the I-85 interchange appears mostly complete:
Most of the work in this section over the past month seems to be concentrated on the placing of a final asphalt layer on the roads that cross the future freeway. The paving and lane striping of Tuttle Road across its bridge has been finished:
Similar work has been done along Poole Road and on Cedar Square Road. The final non-highway bridge that needed construction has been completed, as can be seen in this photo from the Poole Road bridge:
As can be seen though, little or no further work on paving the freeway has occurred either to the north or south of the bridge:
Approaching Cedar Square Road, Poole Road parallels the freeway on the right. There was progress in re-doing Poole Road where it met the former alignment of Cedar Square Road, the road now curves off to the left on a new alignment. The photo of the Cedar Square Road Bridge below is taken where Poole Road now curves toward Cedar Square:
Work has been done on grading the route where the old alignment of Cedar Square was torn down. There, has not been much work on the interchange ramps, however:
Both Cedar Square Road and current US 311 from just south of the intersection below to just north of the former Cedar Square intersection have received their final coat of asphalt:
The water tower in the background is either being replaced or augmented by a new bigger water tower further south on US 311 which has a big 'Welcome to High Point' logo on it. I suppose they hope people will see it from the new freeway.

B. Phase 2
The second phase of construction runs from Spencer Road, 1/2 mile south of Cedar Square, to US 220. This is a design-build contract where work started in late 2008. The major feature of this segment will be an interchange with current US 311 in Sophia and the interchange where I-74 will tie into I-73 (US 220) near Randleman. There is little more than clearing going on at the Sophia interchange so far:
Most of the clearing seems to have been done, seen from US 311 South, the crane indicates the start of some infrastructure construction. There are more interesting things to see on US 220:
Traveling southbound, they are now putting structures in for the I-74 bridges on the right side, the first one is mostly metal and will lead to the I-74 west lanes that are being graded in the vicinity. The second structure is mostly cement and this will take traffic from I-74 east to I-73 north:
This will be a lower bridge, the ramp to I-74 west will be a flyover and go both over US 220 and the other bridge. This requires building a large mound along northbound US 220 for the ramp to the flyover, seen below from the southbound lanes:
One can barely see the top of the future ramp when traveling along in the northbound lanes:
Here's a wider view of the construction scene as viewed going northbound on US 220:
The first phase and East-Belt construction are 86% complete as of the end of March according to NCDOT, the contractors having completed over 3 1/2% of the remaining construction during the month. At this pace the route from Business 85 to Cedar Square Road could be done by the end of July. I will return sometime in May to see if this prediction is still possible.

Comments

Anonymous said…
Signs for 311/Main St in High Point were blown down in last week's tornado. It should be interesting to see what they are replaced with.
Bob Malme said…
Thanks for the information. I have revised the comment regarding the missing Exit 65 signs in light of the new information.

Popular posts from this blog

California State Route 88 the Carson Pass Highway

Between 2016 and 2017 I drove the majority of California State Route 88 from CA 99 in Stockton east over Carson Pass to CA 89.






CA 88 is a 122 mile state highway from CA 99 in Stockton east over the Sierra Nevada Range to the continuation route Nevada State Route 88 at the Nevada State Line.  CA 88 is known as the Carson Pass Highway.  Carson Pass at 8,574 feet above sea level along CA 88 is an all-year Mountain Pass in the Sierras and on occasion designated as Temporary US Route 50 when conditions are bad over Echo Summit. 

CA 88 was not one of the original Signed State Highways.  CA 8 was the original designation over Carson Pass which can be seen on the 1938 California State Highway Map.

1938 State Highway Map

CA 8 was substantially different than CA 88 west of Jackson as it largely follows the current route of CA 26.  From US 99E in 1934 and later US 50/99 in 1936 from Stockton CA 8 originally used the following route to reach Jackson:

-  Legislative Route 5 from US 99 in Stockton …

California State Route 49; The Golden Chain Highway (CA 41 north to CA 16)

Last year I traveled California State Route 49 from CA 16 north to CA 89 in one continuous trip.  This year and in 2016 I traveled the rest of CA 49 south to CA 41 in Oakhurst.  This blog post consists of photos of the highway from that time period and historical information about the southern part of CA 49.


This blog post is meant to be a continuation of the previous one I did regarding CA 49 from CA 16 north to CA 89.  A link to said blog post can be found below:

California State Route 49; The Golden Chain Highway (CA 16 north to CA 89)

As stated in the previous blog post; CA 49 is an approximately 295 mile long north/south highway which traverses the traditional Gold Rush Country of California.  While I intend to discuss county level historical alignments of CA 49 as I did in the first blog post I thought this would be a good place to discuss the backstory of highway.

CA 49 was first signed in 1934 along a series of Legislative Route Numbers ("LRN") that were largely locat…

Caliente-Bodfish Road/Kern County Road 483

Back in 2016 I took Caliente-Bodfish Road south towards California State Route 58 while leaving the Sierra Nevada Range after looking for the town site of Old Kernville.






Caliente-Bodfish Road is also known as Kern County Road 483 which I believe is an internal designation for mountainous roadways within the Sierra Nevada Range.  Caliente-Bodfish Road begins at Kern Canyon Road (Old California State Route 178) at the southern extent of Bodfish and climbs over the southern most extent of the Sierra Nevada Range approximately 35 miles to Bena Road near Caliente.  Caliente-Bodfish Road is a full two-lane road despite traversing some narrow terrain in the Sierras.  The high point on Caliente-Bodfish Road appeared to be near 4,000 feet above sea-level and I would estimate that there grades as high as 10% in places.

South of Bodfish Caliente-Bodfish Road ascends quickly above the community on a series of switchbacks.  There is no official overlook but there is a hell of a view of Bodfish an…