April Tri-Ex Progress Roadtrip Report

As Adam indicated in his previous photo post, we were out Saturday (4/10) checking on the progress of the Triangle Expressway, the Future Toll portions of NC 540 and NC 147. The trip went in the opposite direction as before, so this progress report will start with...
1. The Western Wake Freeway (NC 540):
As seen from the current end of NC 540 looking west, there has been some substantial work on grading the road and the start of installing bridges since our last visit in February:
Both cement and steel bridge supports can be seen. They have piled the material needed for the next bridge project on the median between the unopened lanes of NC 540:
The first major road closure will occur tomorrow (4/12) as explained in this message sign:
McCrimmon Parkway will be closed as a bridge is put in to take the parkway over the freeway.
Here's a view of what they will have to remove:
The parkway is behind the guardrail. The photo was taken from the edge of the Panther Creek High School stadium access road. The stadium bleachers will have a good view of construction, and of the toll road traffic, after completion. Here's the view looking toward NC 55 from where the Parkway bridge will be constructed:
As you can see on the left, there has already been a start to landscaping the highway. The tracks to the right are how contractor vehicles enter and leave the roadbed (with drivers to busy to return a wave). The photo below looks the other direction, south of McCrimmon Parkway:
It appears they are starting bridge construction along the highway in the distance. The cement slab at bottom right is part of a culvert they are building, closeup photo below:
Since last February, construction, has proceeded across Carpenter Fire Station Road in Cary and further south toward US 64. The photo below is looking south along Carpenter...
Here's a view to the north:
As construction moves along, we have tried to find parking areas that are best to observe the construction. The newest one we found is the parking lot for the relatively new USA Baseball complex, here's a photo of the future toll road taken walking from the parking lot to within the toll road's right-of-way:
While most of the construction ends about here, around the curve behind the hill of dirt...
Clearing continues south past Green Level Road East where the contractor has cleared enough space for an office trailer and parking lot for employee vehicles. This is where the first interchange south of NC 55 will be built. The most interesting items in this area are that some houses have not been cleared but are apparently being used by the fire department for training exercises. Here's one that's been mostly burned down:
The tree clearing stops south of Green Level, a little more than a mile north of US 64, the next major route to be affected by the West Wake Freeway construction.

2. The Triangle Parkway (NC 147)
We saw less progress here than on the NC 540 portion, surprising, since this section is only 3 miles long and is supposed to be complete next year. There were some signs of progress at the southern end, as seen below from the current NC 540 Davis Drive offramp:
Some initial construction work and clearing has gone north of here. You can view additional clearing that has taken place south of Davis Drive as it curves back toward Hopson Road:
However, little progress can be seen to the north as viewed from the future Hopson Road bridge and interchange:
Which appears similar to the photos of the area taken in February, except that one of the construction trailers has been moved. A clue to the lack of progress may be seen south of Hopson...
Where currently the high-power electric transmission poles and lines appear to be in the future parkway's right-of-way. Whether this is according to schedule, or is due to a delay in talks with the power company, is not known. Any lag in progress here may threaten to delay the planned opening date of 2011.
They are making progress at the northern end where the current NC 147 meets its future pathway:
The grade has been cut down to meet the current roadway and it appears work on a culvert is starting where the two cranes are located. There is also construction starting along current NC 147 southbound by the I-40 interchange. I will try to find out whether there is any problems that would cause a delay in constructing the parkway before the next update in late May.

Comments

Popular posts from this blog

The Relief Route That Wasn't: The Never Built I-70 Bypass in the Mid-Mon Valley

In June 1963, a small blurb in the Pittsburgh Post-Gazette read that The Westmoreland Engineering Company was awarded a $24,060 bid to study the proposed construction of Interstate 70 in Westmoreland and Washington Counties.  The study was to see what the construction and right-of-way costs "...to modernize the existing highway to Interstate requirements within eight months." (1)  This small, non-attributed, three paragraph article came less than a decade after the completion of a four lane highway that linked the Mid-Mon Valley to the Pennsylvania Turnpike. This would be the start of a 15 year process to upgrade and improve Interstate 70 - a process that ultimately never produced a single foot of new highway.

This is the story, albeit brief, of the I-70 that never came about.

Background:
What is now known as Interstate70 from Washington to New Stanton began as a connecting highway for the region to the Pennsylvania Turnpike.  Known as the "Express Highway", construct…

The Many Failed Plans of Pittsburgh's Wabash Bridge and Tunnel

The December 27, 2004 opening of the Wabash Tunnel ended over 70 years of proposals and speculation for the use of the over 100 year old facility.  The tunnel, which is now a reversible roadway that is an alternative route for rush hour traffic, saw many failed plans during the 20th Century.  These plans included options for mass transit, converted and new bridges for vehicles, and other forms of transportation.

Brief History:
Constructed in 1902-04, the Wabash Bridge and Tunnel was planned and financed by rail mogul, Jay Gould.  Gould began his "Battle of the Wabash" with the established railroads of the city in 1890.  He would finally emerge victorious, but during that struggle, Gould would see many setbacks that would eventually result in the railroad's bankruptcy in 1908.  On October 19, 1903, when the two ends of the bridge were to be joined together over the Monongahela River, the 109' bridge collapsed; killing ten men.  Construction would resume four days later …

A look at Pittsburgh's Saw Mill Run Boulevard

Saw Mill Run Boulevard - Pennsylvania State Route 51 - runs through the narrow Saw Mill Run Valley.  It begins at the intersection of Clairton Road and Provost Road at the City of Pittsburgh Line with Brentwood.  It ends at the West End Circle at the entrance to the West End Bridge.  A four lane highway for its the entire length, Saw Mill Run Boulevard consists of interchanges at the South Portal of the Liberty Tubes and with the Parkway West.  It is an expressway from the Parkway to the West End Circle (West End Bypass).  One of the most well known traffic tie-ups in the Pittsburgh area occurs between Maytide Street and PA 88 (Library Road) which is simply known as 'Maytide and 88.'

History:
Saw Mill Run Boulevard was part of the 1928 Allegheny County 'City Beautiful' bond issue.  The bonds resulted in the creation of Saw Mill Run, Ohio River, Allegheny River and Mosside Boulevards. (1)   After the completion of the Liberty Tunnels in 1924, Downtown Pittsburgh was offic…