July's I-74 /US 311 Freeway Progress Report, Part 1

I decided that I was tired of being hold up in 100 degree weather, and a road trip in the heat would be an excellent test to see how my AC was working. So I left early Sunday morning, to beat the extreme heat, and headed off to High Point and south to once again take note of the latest progress on building the I-74 freeway, still expected to open around November. Since I have been given several other places to check progress on the new section from Spencer Road to US 220, I will be including those photos in Part 2, as well as splitting the two contracts up onto separate pages on my I-74 pages as well.

I. High Point East Belt, Business 85 to I-85
A. Baker Road
In a semi-historic moment, not quite up the meeting of railroads in Utah, Segment 3 of the East Belt was finally joined to Segment 2 earlier in July, as you can see below:
Asphalt now extends from Business 85 to just before Kersey Valley Road, most appears to be the final layers. As you may see in the future westbound lanes, the road is paved well enough at least for bikers to use. The other side shows the new asphalt as well, along with the need for more landscaping before the construction is complete:
As for Baker Road itself, as you can see by the utilities still poking up in the street, a final coating of pavement is still due:
B. Jackson Lake Road
Some work on landscaping here, but the item of most interest is the pile of metal for the future overhead sign for the I-85 exit lying next to the eastbound lanes:
Trucks to put up the sign assembly will come from the still open access path from Jackson Lake Road, which is marked by dirt you can see on the right. Looking eastbound, some landscaping and water containment progress has been made:
With some more progress needed for completion, there may guardrails needed to be placed here also.

C. Kersey Valley Road Bridge and Dresden Road Area
As you can see, most effort has been put into landscaping and guard rails this past month:
Of bigger surprise, was the installation of a BGS assembly for the I-85/NC 62 interchange just to the south/east of the bridge:
Hopefully, the next time there will be some actual signs on some of these overhead assemblies. There still needs to be some work on landscaping and water containment here, as the photo below shows:
The heat isn't helping the former, nor probably the workers trying to do the latter. The only other new item in this area was the construction of a haul road to take the construction materials piled up off Dresden Road to where they are supposed to end up along the freeway:
E. The I-85 interchange
The end of this section shows probable completion of all the bridges including the flyover on the right side:
A closeup on the I-85 bridges, however, shows more landscaping work is needed along the new freeway:
As for I-85 itself, more signs have gone up along the C/D ramps northbound:
II. 'US 311 Bypass' I-85 to Spencer Road
A. I-85 Flyover Ramp
As indicated above, and shown below, this ramp and bridge combination appears to be complete with guardrails now posted at the bridge:
Construction trucks use the ramps to access I-85 which has caused them to put a orange colored merge sign at the end of the C/D ramps northbound.

B. NC 62
Nothing truly new to report here, I hoped for at least a new sign on the existing overhead assembly north of the bridge, but no such luck.

C. Tuttle Road
Better luck here. New sign structures, as well as median guide wires have appeared both north:
And also looking south toward Poole Road:
The sign is barely in view at the end of the curve. All major landscaping appears complete here.

D. Poole Road-Again, nothing new to report here, the final asphalt layer was applied to the creek bridge to the north, and blocked off by barrels, so that no construction truck (or biker) would drive over it.

E. Cedar Square Road and Interchange-
This is where the most work remains to be done. They have applied a base asphalt layer in some areas of the westbound freeway and on the ramps. The eastbound off ramp which traffic will use to leave the freeway temporarily until 2012 still needs a lot of work, as you can see here:
Work still needs to be done also on landscaping and water containment toward the bridge:
There has been some, but not a lot of progress on the westbound onramp, as seen here:
Or from the photo below, from the top of the bridge, which shows the freeway roadbed heading toward the end of this construction segment at Spencer Road.

The remainder of the trip will be featured in part 2. It will feature three new places that will be used to chart progress, including a bridge that already has mostly been completed.

Comments

Popular posts from this blog

The Abandoned New Stanton Interchange Ramps

For nearly 50 years, the Pennsylvania Turnpike interchange with Interstate 70 and US 119 in New Stanton has been a rather free-flowing double trumpet, grade separated interchange between the two freeways.  But for the first 23 years of the turnpike, this interchange was vastly different.  It was the only non-trumpet interchange within the system (excluding termini points) and featured very tricky and gridlock causing left turns within the interchange.  (See image on right).  With the birth of the Interstate Highway System in the mid-1950s, new freeways were built and in many cases the Turnpike kept the original interchange using local roads to connect to the new freeways.  Interchanges with what would become I-81, I-176, I-80, I-70 in Breezewood, and I-79 were left with the original design.

Meanwhile in the 1950's, the state began building a freeway that ran from New Stanton west towards Washington.  This freeway, signed PA 71, was built to connect those in the industrial Mon Valle…

Quemahoning Tunnel

The Quemahoning Tunnel may have never been built by the Pennsylvanina Turnpike Commission, but it still has a history unto itself.  Originally planned to carry rail along the South Penn Railway, the tunnel never would not see any trains until 1909 when a small line named the Pittsburgh, Westmoreland & Somerset began utilizing it.  The use was brief and by the end of 1916 the PW&S was no longer in operation and abandoned the facility.  Twenty-some years later, the newly formed Pennsylvania Turnpike Commission considered using the abandoned tunnel, in fact it was shown on some original plans.  However, the PTC decided against using it, and the tunnel remained empty.

The eastern portal of the Quemahoning Tunnel is easily accessible from the PA Turnpike.  The portal is located at mile 106.3 along the westbound roadway.  The tunnel is one of the many "What Could Have Been's?" of the Pennsylvania Turnpike.  Below, Bill Symons shares photos taken in late Fall of 1986 of …

Conflict in the Mountains: The Story of Corridor H in West Virginia

Corridor H (US 48) was legislatively created as part of the 1965 Appalachian Regional Development Act.  This route which was designated to run east from Weston via Elkins to Strasburg, Virginia has been West Virginia's most controversial route of the six Appalachian Highway Development System routes that run within the state's borders.  The emotional conflict that has led to numerous legal and political struggles has placed the environment, desire for economic and social progress, and the Eastern West Virginia way of life at odds with each other for nearly four decades.

Early History:
The story of Corridor H begins in the 1930s.  Benton McKay, who orchestrated the creation of the Appalachian Trail, suggested a network of highways and parkways throughout Appalachia. (1)  That proposal would become a key part of the 1965 Appalachian Regional Development Act.  The Act included the creation of the Appalachian Development Highway System (AHDS).  The highway system consisted of "…