July's I-74 /US 311 Freeway Progress Report, Part 1

I decided that I was tired of being hold up in 100 degree weather, and a road trip in the heat would be an excellent test to see how my AC was working. So I left early Sunday morning, to beat the extreme heat, and headed off to High Point and south to once again take note of the latest progress on building the I-74 freeway, still expected to open around November. Since I have been given several other places to check progress on the new section from Spencer Road to US 220, I will be including those photos in Part 2, as well as splitting the two contracts up onto separate pages on my I-74 pages as well.

I. High Point East Belt, Business 85 to I-85
A. Baker Road
In a semi-historic moment, not quite up the meeting of railroads in Utah, Segment 3 of the East Belt was finally joined to Segment 2 earlier in July, as you can see below:
Asphalt now extends from Business 85 to just before Kersey Valley Road, most appears to be the final layers. As you may see in the future westbound lanes, the road is paved well enough at least for bikers to use. The other side shows the new asphalt as well, along with the need for more landscaping before the construction is complete:
As for Baker Road itself, as you can see by the utilities still poking up in the street, a final coating of pavement is still due:
B. Jackson Lake Road
Some work on landscaping here, but the item of most interest is the pile of metal for the future overhead sign for the I-85 exit lying next to the eastbound lanes:
Trucks to put up the sign assembly will come from the still open access path from Jackson Lake Road, which is marked by dirt you can see on the right. Looking eastbound, some landscaping and water containment progress has been made:
With some more progress needed for completion, there may guardrails needed to be placed here also.

C. Kersey Valley Road Bridge and Dresden Road Area
As you can see, most effort has been put into landscaping and guard rails this past month:
Of bigger surprise, was the installation of a BGS assembly for the I-85/NC 62 interchange just to the south/east of the bridge:
Hopefully, the next time there will be some actual signs on some of these overhead assemblies. There still needs to be some work on landscaping and water containment here, as the photo below shows:
The heat isn't helping the former, nor probably the workers trying to do the latter. The only other new item in this area was the construction of a haul road to take the construction materials piled up off Dresden Road to where they are supposed to end up along the freeway:
E. The I-85 interchange
The end of this section shows probable completion of all the bridges including the flyover on the right side:
A closeup on the I-85 bridges, however, shows more landscaping work is needed along the new freeway:
As for I-85 itself, more signs have gone up along the C/D ramps northbound:
II. 'US 311 Bypass' I-85 to Spencer Road
A. I-85 Flyover Ramp
As indicated above, and shown below, this ramp and bridge combination appears to be complete with guardrails now posted at the bridge:
Construction trucks use the ramps to access I-85 which has caused them to put a orange colored merge sign at the end of the C/D ramps northbound.

B. NC 62
Nothing truly new to report here, I hoped for at least a new sign on the existing overhead assembly north of the bridge, but no such luck.

C. Tuttle Road
Better luck here. New sign structures, as well as median guide wires have appeared both north:
And also looking south toward Poole Road:
The sign is barely in view at the end of the curve. All major landscaping appears complete here.

D. Poole Road-Again, nothing new to report here, the final asphalt layer was applied to the creek bridge to the north, and blocked off by barrels, so that no construction truck (or biker) would drive over it.

E. Cedar Square Road and Interchange-
This is where the most work remains to be done. They have applied a base asphalt layer in some areas of the westbound freeway and on the ramps. The eastbound off ramp which traffic will use to leave the freeway temporarily until 2012 still needs a lot of work, as you can see here:
Work still needs to be done also on landscaping and water containment toward the bridge:
There has been some, but not a lot of progress on the westbound onramp, as seen here:
Or from the photo below, from the top of the bridge, which shows the freeway roadbed heading toward the end of this construction segment at Spencer Road.

The remainder of the trip will be featured in part 2. It will feature three new places that will be used to chart progress, including a bridge that already has mostly been completed.

Comments

Popular posts from this blog

Memphis & Arkansas Bridge (Memphis, TN)

  Like the expansion of the railroads the previous century, the modernization of the country’s highway infrastructure in the early and mid 20th Century required the construction of new landmark bridges along the lower Mississippi River (and nation-wide for that matter) that would facilitate the expected growth in overall traffic demand in ensuing decades. While this new movement had been anticipated to some extent in the Memphis area with the design of the Harahan Bridge, neither it nor its neighbor the older Frisco Bridge were capable of accommodating the sharp rise in the popularity and demand of the automobile as a mode of cross-river transportation during the Great Depression. As was the case 30 years prior, the solution in the 1940s was to construct a new bridge in the same general location as its predecessors, only this time the bridge would be the first built exclusively for vehicle traffic. This bridge, the Memphis & Arkansas Bridge, was completed in 1949 and was the third

Old River Lock & Control Structure (Lettsworth, LA)

  The Old River Control Structure (ORCS) and its connecting satellite facilities combine to form one of the most impressive flood control complexes in North America. Located along the west bank of the Mississippi River near the confluence with the Red River and Atchafalaya River nearby, this structure system was fundamentally made possible by the Flood Control Act of 1928 that was passed by the United States Congress in the aftermath of the Great Mississippi River Flood of 1927 however a second, less obvious motivation influenced the construction here. The Mississippi River’s channel has gradually elongated and meandered in the area over the centuries, creating new oxbows and sandbars that made navigation of the river challenging and time-consuming through the steamboat era of the 1800s. This treacherous area of the river known as “Turnbull’s Bend” was where the mouth of the Red River was located that the upriver end of the bend and the Atchafalaya River, then effectively an outflow

California State Route 203 the proposed Minaret Summit Highway

California State Route 203 is an approximately nine-mile State Highway located near Mammoth Lakes in the Sierra Nevada Mountains of Mono County.  California State Route 203 as presently configured begins at US Route 395, passes through Mammoth Lakes and terminates at the Madera County line at Minaret Summit.  What is now California State Route 203 was added to the State Highway System in 1933 as Legislative Route Number 112.  The original Mammoth Lakes State Highway ended at Lake Mary near the site of Old Mammoth and was renumbered to California State Route 203 in 1964.  The modern alignment of the highway to Minaret Summit was adopted during 1967.   The corridor of Minaret Summit and Mammoth Pass have been subject to numerous proposed Trans-Sierra Highways.  The first corridor was proposed over Mammoth Pass following a Southern Pacific Railroad survey in 1901.  In 1931 a corridor between the Minarets Wilderness and High Sierra Peaks Wilderness was reserved by the Forest Service for po