I-74/US 311 Freeway Progress for August, Part 1

I traveled Sunday 8/29 to view the latest progress on the I-74/US 311 Freeway between Business 85 in High Point and US 220 in Randleman, plus check up on the new construction project along 220 in Asheboro. During the visit from Cedar Square Road south I followed along with Bill Travers, a local resident who has been helping me keep up to date on area construction projects. Part 1 will describe progress on Phase 1 of the project from Business 85 to Spencer Road, while Part 2 will describe progress and new locations to view Phase 2 to US 220 and remark about changes in plans for this part of highway since the Design-Build section was let.

Part 1 - Business 85 to Spencer Road
A. Baker Road
As seen in the photo below, the last grading of the temporary road has been completed, the ground now needs seeding and wet weather for something to grow on it:
The views to the south and north actually look less complete than last month due to landscaping work covering up the completed asphalt roadway. Here's a view to the north:
They also seem to be laying cable along the side of the roadway. The view to the south:
shows the need for more landscaping toward the bridge and covers for the median catch basins.

B. Jackson Lake Road Bridge
Some changes here, beginning with the landscaping around the bridge. The former truck entry road has been graded over and become a grassy area:
This is a definite sign construction is wrapping up in this area, another sign are signs, or structures to hold them placed in both directions west of the bridge:
The left gantry is for the I-85 exit, the one on the left Business 85. Remaining landscaping has to be completed as well as sign placement. Looking east also shows some landscaping work remains...
Plus catch basin work. Though there is an addition of shoulder guard rails and median guide wires.

C. Kersey Valley Road Bridge
Major progress in this area on guard rails, as one can see in the photo below:
The truck access road, seen in the foreground, is still being used. Looking south reveals more guardrail progress as well as successful landscaping that almost needs to be mowed...
They also need to put up another sign gantry, I assume this is the 2 mile sign for the Business 85 Exit. Successful landscaping along the eastbound roadway has been mixed:
You would think more effort would be made to get the slope to look good, because the Blythe Construction contractor offices are located at the top of the hill. Looking at the I-85 interchange from Dresden Road...
It appears most of the work has been completed, though this is from some distance away.

D. NC 62, Tuttle Road, and Poole Road showed little change with similar need for completing some landscaping, adding some guardrails, and completing catch basins.

E. Cedar Square Valley Bridge and Interchange
Most of the remaining paving needed to open the road has been completed, as seen looking north from the Cedar Square Road Bridge back toward the Poole Road bridge...
The eastbound off ramp is completed as well as the westbound lanes back to the Cedar Square on ramp. The view below is of the completed on ramp intersection with Cedar Square Rd...
The construction equipment in the distance is grading the remaining roadbed toward Spencer Road. This is what it looks like from the bridge:
The paving of this section has been transferred to the Barnhill Construction, the firm doing the design/build phase 2 of the project. The contractor for Phase 1, Blythe Construction was having trouble this spring purchasing enough asphalt for its many projects. The equipment seen in the distance is actually on the other side of Spencer Road. Construction from there to US 220 will be the subject of the second part of this report.

Comments

Bob Malme said…
An update as to completion progress. According to the NCDOT Construction Progress Report, the Business 85 to Spencer Road portion was 93.56% complete as of the end of August.

Popular posts from this blog

The story behind the ghost ramps around Pittsburgh International Airport

The roads around Pittsburgh International Airport have a lot of history and intrigue.  The growth of the airport and resulting land acquisitions has changed the routing of many roads in Western Allegheny County.  As the airport grew and traffic around the airport increased, the need for new roads would also change the landscape.  Of course, the fact that this is Pittsburgh means there were also plans for highways that never came to be.  Two of these never built highway plans, the Beaver Valley Expressway (BVE) extension and the full-speed connection to the Southern Expressway at Flaugherty Run Road have traces - specifically ghost ramps - of highways that never came to be.

Beaver Valley Expressway Extension:

For close to three decades this unused piece of roadway along the southern end of Beaver Valley Expressway puzzled Pittsburgh area travelers.  Located near the current-day maintenance hangers for Pittsburgh International Airport, this concrete stub of a highway was supposed to be …

Quemahoning Tunnel

The Quemahoning Tunnel may have never been built by the Pennsylvanina Turnpike Commission, but it still has a history unto itself.  Originally planned to carry rail along the South Penn Railway, the tunnel never would not see any trains until 1909 when a small line named the Pittsburgh, Westmoreland & Somerset began utilizing it.  The use was brief and by the end of 1916 the PW&S was no longer in operation and abandoned the facility.  Twenty-some years later, the newly formed Pennsylvania Turnpike Commission considered using the abandoned tunnel, in fact it was shown on some original plans.  However, the PTC decided against using it, and the tunnel remained empty.

The eastern portal of the Quemahoning Tunnel is easily accessible from the PA Turnpike.  The portal is located at mile 106.3 along the westbound roadway.  The tunnel is one of the many "What Could Have Been's?" of the Pennsylvania Turnpike.  Below, Bill Symons shares photos taken in late Fall of 1986 of …

Roebling Aqueduct

In a quiet and often overlooked corner of Northeastern Pennsylvania, the country's oldest surviving suspension bridge crosses the Delaware River into New York.  The Delaware Aqueduct, designed and built by famed engineer John A. Roebling, has withstood a very colorful history from being an important piece in the region's transportation, to uncertainty during the growth of rail, nearly eight decades of neglect and poor management as a private toll bridge, to finally being restored by the National Park Service and in use as an automobile bridge today.

Construction and Canal Era (1847-1898):
During the 1840's, the Delaware & Hudson Canal was looking at ways to speed up service along its route.  One of the major bottlenecks was where the canal reached the Delaware River.  Since it began operation in 1828, the D&H used a rope ferry to pull traffic along to Canal across the Delaware.  The conflicting traffic of vessels going down the Delaware to Trenton or Philadelphia and…