I-74/US 311 Freeway Progress for August, Part 1

I traveled Sunday 8/29 to view the latest progress on the I-74/US 311 Freeway between Business 85 in High Point and US 220 in Randleman, plus check up on the new construction project along 220 in Asheboro. During the visit from Cedar Square Road south I followed along with Bill Travers, a local resident who has been helping me keep up to date on area construction projects. Part 1 will describe progress on Phase 1 of the project from Business 85 to Spencer Road, while Part 2 will describe progress and new locations to view Phase 2 to US 220 and remark about changes in plans for this part of highway since the Design-Build section was let.

Part 1 - Business 85 to Spencer Road
A. Baker Road
As seen in the photo below, the last grading of the temporary road has been completed, the ground now needs seeding and wet weather for something to grow on it:
The views to the south and north actually look less complete than last month due to landscaping work covering up the completed asphalt roadway. Here's a view to the north:
They also seem to be laying cable along the side of the roadway. The view to the south:
shows the need for more landscaping toward the bridge and covers for the median catch basins.

B. Jackson Lake Road Bridge
Some changes here, beginning with the landscaping around the bridge. The former truck entry road has been graded over and become a grassy area:
This is a definite sign construction is wrapping up in this area, another sign are signs, or structures to hold them placed in both directions west of the bridge:
The left gantry is for the I-85 exit, the one on the left Business 85. Remaining landscaping has to be completed as well as sign placement. Looking east also shows some landscaping work remains...
Plus catch basin work. Though there is an addition of shoulder guard rails and median guide wires.

C. Kersey Valley Road Bridge
Major progress in this area on guard rails, as one can see in the photo below:
The truck access road, seen in the foreground, is still being used. Looking south reveals more guardrail progress as well as successful landscaping that almost needs to be mowed...
They also need to put up another sign gantry, I assume this is the 2 mile sign for the Business 85 Exit. Successful landscaping along the eastbound roadway has been mixed:
You would think more effort would be made to get the slope to look good, because the Blythe Construction contractor offices are located at the top of the hill. Looking at the I-85 interchange from Dresden Road...
It appears most of the work has been completed, though this is from some distance away.

D. NC 62, Tuttle Road, and Poole Road showed little change with similar need for completing some landscaping, adding some guardrails, and completing catch basins.

E. Cedar Square Valley Bridge and Interchange
Most of the remaining paving needed to open the road has been completed, as seen looking north from the Cedar Square Road Bridge back toward the Poole Road bridge...
The eastbound off ramp is completed as well as the westbound lanes back to the Cedar Square on ramp. The view below is of the completed on ramp intersection with Cedar Square Rd...
The construction equipment in the distance is grading the remaining roadbed toward Spencer Road. This is what it looks like from the bridge:
The paving of this section has been transferred to the Barnhill Construction, the firm doing the design/build phase 2 of the project. The contractor for Phase 1, Blythe Construction was having trouble this spring purchasing enough asphalt for its many projects. The equipment seen in the distance is actually on the other side of Spencer Road. Construction from there to US 220 will be the subject of the second part of this report.

Comments

Bob Malme said…
An update as to completion progress. According to the NCDOT Construction Progress Report, the Business 85 to Spencer Road portion was 93.56% complete as of the end of August.

Popular posts from this blog

The story on how the unbuilt US 40 Expressway in Brownsville took 40 years to complete.

For nearly four decades, the four lane US 40 just east of Brownsville came to an abrupt end - shown in the photo above - at Grindstone Road in Redstone Township.   In the late 1960s, what was then the Pennsylvania Division of Highways (PennDOH) extended a new four lane alignment of US 40 eastwards from Broadway Street slightly over one mile to Grindstone Road where an incomplete diamond interchange was built.  Earlier in the decade, PennDOH had built a four lane US 40 in Washington County into Brownsville complete with a new crossing over the Monongahela River known as the Lane Bane Bridge.  This new highway and bridge allowed US 40 to bypass the older Intercounty Bridge and downtown Brownsville. 

After this new highway opened, nothing would happen to it for nearly forty years.  US 40 traffic would use the ramps for this planned diamond interchange and then jog on Grindstone Road briefly before continuing towards Uniontown on the original National Road. 
What is unknown (at least to…

The story of the Boy Scout Ramps on Interstate 79 North in NW Pennsylvania

If you are traveling on Interstate 79 North of Pittsburgh, you may notice the remnants of a set of off and on ramps at mile 100 just north of Exit 99 (US 422).  There's a story behind these ramps.  Forty years ago, these ramps were built specifically for two Boy Scout Jamboree's that were held at Moraine State Park - 1973 and 1977.  The ramps purpose were to provide access to the north shore of Lake Arthur where the bulk of the festivities and campsite for the Jamboree were located.  (Lawrence County Memories has a great write up and map of the festivities on its site.)

Not long after the Jamboree ended the ramps were abandoned.  There are still remnants of the Boy Scout Ramps today.



Above: Sattelite view of the Boy Scout Jamboree Ramps. 
Below: A view of the ramps from I-79 South.



The google street view image above gives a view along West Park Road of where the set of ramps intersected the highway.  The ramps provided direct access to North Shore Drive (which is the right tur…

The few clues of the Northern Durham Parkway

Sometimes when you look through a box of maps for the first time in five years, you come across something you may have easily over looked.  Such was the case when I found a 2004 (so rather recent) map of Raleigh.  This map was made by the Dolph Map Company for WakeMed.  In the Northwestern corner of Wake County, there were two items to the map showing roads that are still not in existence 13 years later.

The road is the Northern Durham Parkway - this is a proposed 19 mile highway from US 501 north of Durham to the Raleigh-Durham International Airport.  The first proposals for this highway date back to 1967 when Eno Drive-Gorman Road was listed on the Durham Area Thoroughfare Plan. (1)  Other proposals called the highway the Northwest and Northeast Durham Loop. (2)  The route would serve as a northern and eastern bypass of Durham almost serving as a near loop.  The route was fought vigorously for three decades by the Eno River Association citing concerns for the the Eno River, nearby n…