Labor Day Triangle Parkway Progress Report

With others in the blog crew busy, or away for Labor Day, I decided to see what progress has been made on the Durham section of the Triangle Expressway, the Triangle Parkway since July. I'll wait for when others from the Wake County contingent are interested to explore progress on the part to the south, the Western Wake Freeway. The tour starts from the northern end of the parkway at I-40 and works down to the end at NC 540. The following of note was seen:

1. I-40 Interchange
Some progress has been made in building a more high-speed off ramp from I-40 East. The ramp roadbed continues along the jersey barrier to the south, which I assume will become a merging third lane. Notice the I-40 overhead exit sign. It is one of the new 'highly reflective', needs no lighting, signs that have gone up along the Durham Freeway. The new sign, however, does not have an exit number.

2. NC 54 Bridge
From the previous visit, the impression of the construction was that it was simply going to be a slight movement of the existing bridge to the north. The latest photos, though:
Imply a totally new bridge to the north, possible using some of the existing bridge. Support girders seen above are similar to those at other permanent bridges. Clearing of the other side of the highway is proceeding, so support structures can be placed there as well. The photo below:
Shows how the new bridge may tie in to the old one. Perhaps this is being done so the existing freeway can be slightly re-aligned to the south of the bridge to better join the new parkway.

3. The New Parkway Connection
More progress has been made on the connection from the existing NC 147 to the new parkway as seen in this view from NC 54:
From this view one can see how the route of the Parkway curves around the EPA's property to the right of the Parkway on the way toward Hopson Road. This is the view from 147 South:
There are no signs that the closing of the connection to Alexander Drive will happen in the immediate future.

4. Hopson Road Bridge/Interchange
More clearing has been completed in this area, but no bridge construction has started, as can be seen in this view approaching the site from the west:
Looking south one can see the other end of the interchange area at Davis Drive and beyond:
You are looking down the Parkway mainline. The cranes in the distance are working on the Davis Drive bridge (more details below), to the middle right you can also see bridge construction for the southbound C/D ramp that will run between Hopson and Davis. Looking to the north:
One can see great progress on the road bed beyond the bridge, but that they are still in the first phases of constructing the north side of the bridge itself. They may also still have to deal with utility lines to the south of Hopson Road:
There's also unfortunate news for our favorite place to park to observe progress here, looks like the temporary relocation of Hopson Road will be cutting through 'our' parking lot:
Looking West, with Hopson Road seen below the utility wires. The remote lot is behind the black plastic, the road appears it will use the lot to make it back to Hopson before the building's main parking lot driveway.

5. Davis Drive Bridge and Interchange
The most complete bridge construction on the Parkway can be seen at Davis Drive:
This is to the south of the road, note the 'extras' in the bridge supporting structure, it will include bricks as well as fancy pre-cast cement pieces. They haven't quite finished the brickwork:
Having completed about 2/3 of the work on the far right of the bridge. As a comparison:
The view across Davis is disappointing, with only the bridge landscape work completed. They are also though working on the bridge for the southbound C/D lanes to cross Davis west of the main bridge:
It will be smaller, but I assume will have the same alternating cement and brick design. Since there was a truck ramp to the top of the bridge, I decided to climb it to see the view:
The view to the south takes you almost to Kit Creek Parkway, or what's left of it.
While the view north of the back of the bridge structure is not as interesting as the front:
7. Kit Creek Parkway Bridge and NC 540 Interchange
As RTP travelers know, the Davis Drive exit from NC 540 was closed at the start of Parkway construction. There were two reasons, the need to extend Kit Creek Parkway across the Triangle Parkway via a new bridge and to recreate the existing Davis Drive interchange into the start of the Triangle Parkway. Here's a view of progress so far on the Kit Creek Bridge:
As can be seen, two of the three support structures for the bridge have received their concrete coverings. Here's a view of progress on the bridge structure to the west:
The metal girders have been installed, but not all the precast cement structures have been placed, several are piled up in the construction area:
As for Kit Creek Parkway, it will be put on a new alignment to the south of the existing road to take it over the bridge:
It appears the road will be narrower than the existing road, with perhaps separate entrances to the company to the right:
The view to the north of the future bridge back toward Davis Drive shows progress on grading and an impressive collection of large earth moving equipment:
As for the NC 540 interchange. The photo below is looking south on the Parkway in the direction of NC 540, which cannot be seen due to a sloping hill and piles of construction materials:
They appear to be starting to work on connecting the new Parkway to the existing 'Davis Drive' ramp from NC 540. It appears the roadway from the existing ramp will have to be moved slightly to the left to connect with the new roadway, the east supports of the Kit Creek Bridge are on the left:
I hope to be able to take a longer road trip to view the Wake County portion of the Triangle Expressway sometime in September.

Comments

Popular posts from this blog

California State Route 88 the Carson Pass Highway

Between 2016 and 2017 I drove the majority of California State Route 88 from CA 99 in Stockton east over Carson Pass to CA 89.






CA 88 is a 122 mile state highway from CA 99 in Stockton east over the Sierra Nevada Range to the continuation route Nevada State Route 88 at the Nevada State Line.  CA 88 is known as the Carson Pass Highway.  Carson Pass at 8,574 feet above sea level along CA 88 is an all-year Mountain Pass in the Sierras and on occasion designated as Temporary US Route 50 when conditions are bad over Echo Summit. 

CA 88 was not one of the original Signed State Highways.  CA 8 was the original designation over Carson Pass which can be seen on the 1938 California State Highway Map.

1938 State Highway Map

CA 8 was substantially different than CA 88 west of Jackson as it largely follows the current route of CA 26.  From US 99E in 1934 and later US 50/99 in 1936 from Stockton CA 8 originally used the following route to reach Jackson:

-  Legislative Route 5 from US 99 in Stockton …

California State Route 85

Last week I had the opportunity to try out several Bay Area roadways.  The first route on my list was California State Route 85 from CA 17 west to US Route 101.






CA 85 is an approximately 24 mile freeway starting at US 101 in San Jose which loops back to US 101 in Mountain View.  I drove the entire route back in 2016 but my recent trip had me starting CA 85 at about the mid-way point in Los Gatos from CA 17 northbound.





CA 85 west of CA 17 briefly skirts the City limits of San Jose before entering Saratoga.





CA 85 dips back into the westernmost limits of San Jose at De Anza Boulevard.  De Anza Boulevard was part of the original surface alignment of CA 9.





CA 85 in Cupertino is the location with the junction with I-280.  The section of CA 85 north of I-280 is the original part of the freeway which means there is plenty of button-copy shields still posted.











CA 85 briefly dips into Sunnyvale before entering Mountain View.   CA 85 encounters CA 82 which runs on the El Camino Real which obvious…

California State Route 49; The Golden Chain Highway (CA 41 north to CA 16)

Last year I traveled California State Route 49 from CA 16 north to CA 89 in one continuous trip.  The prior two years I traveled the rest of CA 49 south to CA 41 in Oakhurst.  This blog post consists of photos of the highway from that time period and historical information about the southern part of CA 49.






This blog post is meant to be a continuation of the previous one I did regarding CA 49 from CA 16 north to CA 89.  A link to said blog post can be found below:

California State Route 49; The Golden Chain Highway (CA 16 north to CA 89)

As stated in the previous blog post; CA 49 is an approximately 295 mile long north/south highway which traverses the traditional Gold Rush Country of California.  While I intend to discuss county level historical alignments of CA 49 as I did in the first blog post I thought this would be a good place to discuss the backstory of highway.

CA 49 was first signed in 1934 along a series of Legislative Route Numbers ("LRN") that were largely located…