I-74/US 311 Randolph County Progress Report

While on the trip taking photos previously posted of the near finished I-74/US 311 freeway, I also took some photos of the Design/Build Section between Spencer Road and US 220. Currently behind schedule at 41% complete (ideally 50% would be completed by now), there has been some progress, particularly in the southern part of the project since I last visited.

A. Spencer Road and Banner Whitehead Road
Not much progress hear except the moving around of some construction equipment. As can be seen in the photo south of Spencer Road, no grading of the future roadway has begun yet:
B. Branson Davis Road
This road features both a new alignment and bridge and the creation of an access road back to a farm on Nelson Park Road which is being cutoff by the freeway. Here's a photo looking north back at Nelson Park, the new access road is to the right paralleling the westbound lanes:
Across the road the alternate alignment and bridge are being built. Here looking south is where the bridge for the new road will go:
A better view can be seen from Walker Mill Road in the distance.

C. Walker Mill Road
Looking north, here's the view of construction on Branson Davis Road:
Here you can see the mound being built to take the freeway over Branson Davis. Looking South one can see progress in clearing and almost up to the current US 311 construction area, around the curve.
D. Current US 311 Interchange
The big news here is that the concrete deck for the main bridge over the freeway has been poured:
It was still being protected by the elements by a plastic covering, some of which had blown off. There hasn't been much progress on completing the roadway to the west, or east, below:
There has been more progress, however, on creating the eastbound on and off ramps:
The construction of the roadway stops currently at the train tracks to the south of current US 311, but picks up afterwords. The consensus is the 311 traffic will be moved to the new road and the old alignment will serve as a temporary railroad bed as a bridge is built on the current rail bed to carry trains over the freeway.

E. Plainfield Road
More progress on the bridge to carry the road over the freeway, but some work has been delayed by recent rain (workers were out at this location apparently trying to catch up when I was there). Notice the water under the freeway bridge support:
Work has progressed much faster on building the west end of the bridge:
The workers there on Sunday were working on the access road to the farm on Old Courthouse Road that will be cutoff from the freeway. Looking into the distance one can see the road where it will be cutoff and further to the bridge on Heath Dairy Road.
Less progress can be seen looking north across Plainfield Road which is acting as a bypass to the bridge construction:
Though there were construction vehicles present, no one was using them at the time.

F. Heath Dairy Road
Progress has been made on the bridge and the grading of the roadway underneath. Here is a view of the entire bridge:
Sorry, if anyone has a sudden urge to go. Notice the disparate design elements on either side. On the east side the wall is vertical on the side and under the bridge, the side includes the wall pieces seen on many new NC bridges. To the west, the cement wall under the bridge is inclined with no element to meet the new roadway. Grading continues on the freeway toward US 220. The work seems to be mostly on the future westbound lanes:
This may be due to ramp construction on US 220, see below. The eastbound lanes as a comparison:
The roadbed here needs more work, at the top of the hill is where the US 220 (I-73) South ramp is to begin. Looking north from Heath Dairy ones sees the opposite of the view from Plainfield Road:
One can see the start of drainage work has begun, along with landscaping near Old Courthouse.
Finally, it's hard to tell if much work has been done on the new road alignment west of the bridge in the past month:
G. US 220 Interchange
While some progress can be seen on the flyover ramps, the most obvious change is work being done on the southbound 220 on and off ramps:
This is the future on ramp to I-74 West with both road grading and landscape work being done.
From 220 Northbound one can get a good look at the future I-74 East on ramp:

Heading southbound again, both the ramp bridges appear similar to photos from the month before, the eastbound US 220 north on ramp:
Heading South again And the future flyover ramp bridge for I-74 West:
Work on the bridge deck is apparently proceeding as shown by the spread of wood sheeting under the bridge, southbound anyway, to protect cars from falling debris. There doesn't seem to be much progress on the flyover ramp heading back northbound:
You may also notice something has disappeared, the previous Future I-73 and I-74 signs.
Closer to the ramp bridges, one can see progress in landscaping:
Closing in on the future ramp bridge carrying traffic to US 220 Northbound one can also see progress on landscaping:
The future 'loop ramp' carrying traffic from I-74 eastbound to North 220 (I-73) can be seen under construction on the right beyond the cement barriers.

I plan to visit the area for one last look on Sunday, October 24 before I move to Massachusetts. I will post any photos showing any significant progress on the blog next week.

Comments

Bob Malme said…
NCDOT lists the freeway as 96.75% complete as of the end of October. Local residents inform me that lines have been put down and signs are starting to go up as of 11/5. No notice from NCDOT on an opening day, yet.
Anonymous said…
Checked with Barnhill Contracting around the middle of April and was told they were expecting to open 74 on May 27th (Memorial Day)

Popular posts from this blog

Check the box: Interstate 495 to 87 conversion administratively approved

The American Association of State Highway and Transportation Officials have recently approved North Carolina's application to remove the short-lived Interstate 495 and future I-495 from Raleigh to Rocky Mount.  This administrative move most likely will result in North Carolina signing Interstate 87 and Future I-87 on the entire corridor in the near future.

Approved in 2013, Interstate 495 was first signed in 2014 along US 64 from Interstate 440 in Raleigh to Interstate 540 in Knightdale.  The remaining segment of highway to Rocky Mount was signed as Future Interstate 495.  However, in 2016, North Carolina's congressional legislators were able to get language in the 2015 FAST ACT designating the US 64/US 13/US 17 corridor from Raleigh to Norfolk as an Interstate.  In 2016, the FHWA and AASHTO designated this entire corridor (including the existing Interstate and Future 495) as Interstate 87.  (NCDOT had applied for Interstate 89 along this route.)

It is currently unknown when t…

The story on how the unbuilt US 40 Expressway in Brownsville took 40 years to complete.

For nearly four decades, the four lane US 40 just east of Brownsville came to an abrupt end - shown in the photo above - at Grindstone Road in Redstone Township.   In the late 1960s, what was then the Pennsylvania Division of Highways (PennDOH) extended a new four lane alignment of US 40 eastwards from Broadway Street slightly over one mile to Grindstone Road where an incomplete diamond interchange was built.  Earlier in the decade, PennDOH had built a four lane US 40 in Washington County into Brownsville complete with a new crossing over the Monongahela River known as the Lane Bane Bridge.  This new highway and bridge allowed US 40 to bypass the older Intercounty Bridge and downtown Brownsville. 

After this new highway opened, nothing would happen to it for nearly forty years.  US 40 traffic would use the ramps for this planned diamond interchange and then jog on Grindstone Road briefly before continuing towards Uniontown on the original National Road. 
What is unknown (at least to…

Starrucca Viaduct

Even older than the Tunkhannock Viaduct is the Starrucca Viaduct, built in 1848. Located in the far northeastern Pennsylvania borough of Lanesboro, this impressive bridge carried the New York and Erie Railroad over a valley as well as the Starrucca Creek and is currently the oldest stone arch railroad in the Commonwealth of Pennsylvania (1). An engineering marvel of its time, and even in today's world, the 1080 foot length, 100 foot height and 25 foot width (2) of the viaduct is simply spectacular. Using local materials such as Pennsylvania bluestone, the Starrucca Viaduct has stood the test of time.With a price estimated at $325,000 in 1848 dollars, the bridge was one of the largest and costliest stone arch railroad bridges built in America at its time (3) . However, the very material that made it expensive to build gave the Starrucca Viaduct much durabilitycompared to other viaducts built in that era.