ODOT tags $809 million for possible I-74 extension in Cincinnati

North Carolina may no longer be alone in building/extending I-74 to South Carolina.  The Ohio Department of Transportation recently tagged $809 million for an Interstate 74 extension to the eastern suburbs of Cincinnati.  The $809 million comes from ODOT's 2011-2015 Major New Construction Program List.

I-74 would be extended from its current eastern terminus along I-75 North to the Norwood Lateral (OH 562).  I-74 would follow OH 562 eastwards to I-71 and head North to around Exit 9 (Red Bank Road).  Red Bank Road to US 50 would be upgraded to Interstate standards.  Then a new freeway would be built eastwardly over the Miami River to OH 32 near Bells Lane.  OH 32 would be upgraded (via grade separations) to an Interstate to Old OH 74 east of I-275.  (This would include a redesign of the current OH 32/I-275 Interchange.)

Map of I-74 Cincinnati extension (UrbanCincy.com)

Currently, ODOT is in the process of rebuilding I-75 in the vicinity of the I-74 and Norwood Lateral interchanges.  The Mill Creek Expressway Project, a total rebuild of I-75, consists of eight different major projects and scheduled to be completed in 2020.  

The $809 million that ODOT has targeted for the I-74 project is broken down into four sections.  Section 1: $204.6 million to upgrade Red Bank Road to an Interstate from I-71 to US 50.  Section 2: $366.2 million for a new highway from US 50, over the Miami River, to OH 32 near Bells Lane.  Section 3: $178.9 million for upgrades to OH 32 from Bells Lane to I-275 including modifications to the OH 32/I-275 interchange.  Section 4: $61.4 million to upgrade OH 32 to Interstate standards from Eastgate Blvd. to Old Ohio Route 74.

ODOT does not list any planned upgrades to the Norwood Lateral or Interstate 71.  The Norwood Lateral would need a significant overhaul to meet modern Interstate standards.  

The jury is out whether or not this extension will ever happen.  But it is an interesting development in the I-73/74 saga.

Story Link: $809M tagged to extend I-74 through Hamilton County ---Cincinnati Business Courier

HT: Frank Brosnan

Comments

Froggie said…
It's not ODOT who's tagging this as an I-74 extension. It's local activist groups that are generally opposed to the OH 32/"Eastern Arterial" portion of the project.
John Bronson said…
Agreed, and in the UrbanCincy blog post, I called out Jake Mecklenburg's far reaching commentary on that. It was nothing more than opinion and guesswork. If anything, all that is programmed in for any future improvements is what Clermont County has been eying for capacity improvements and interchange construction along OH 32.
concerned taxpayer said…
Of course ODOT isn't saying anything. Their plans are a vague spaghetti-like meshwork to keep homeowners and businesses in the dark about where the highway will run. Newtown is strongly opposed to the highway, now that the Village understands what's being planned. The I-74/73 connector plan is part of the federal highway priority corridors, and it doesn't take much effort to find Southwest Ohio politicians in favor of turning the Eastern Corridor highway into an interstate. Two highways already serve this area, and they're barely a mile apart. Why spent a billion dollars on a road that's not needed??? What happened to the Tea Party when you need them?
Anonymous said…
Let the construction of I-74 East, through the Greater Cincinnati area begin, starting with renovating the Norwood Lateral, Red Bank Rd. and Ohio 32 into interstate status. Cincinnati needs a major east-west interstate highway going through the area, and it's I-74. I-74 West goes to the Greater Indianapolis area, so constructing I-74 East should go to the Greater Huntington-Ashland area, entering West Virginia through Chesapeake. The Only portions of I-74 East that should be built is the area, splitting off Ohio 32, west of Piketon and turning southeast toward the proposed Portsmouth bypass in Lucasville, where it meets up with I-73, which will be Huntington's main north-south interstate highway. Both I-73 and I-74 will run concurrently along the Ohio River to Chesapeake, then cross into West Virginia, join up with I-64 West, from Huntington's west side to Kenova, then turn southward to Bluefield, before both interstates split into two separate directions. Interstate 73, on the other hand, can be constructed through renovation of U.S. 52, between Huntington and Portsmouth, U.S 23 South, between Portsmouth and Columbus, then route I-73 along the eastern corridor of I-270 and reconnect with U.S. 23 North. Route I-73 with U.S. 23 North, between Columbus and Findlay, where it would join up with I-75, between Findlay and Perrysburg and I-475, between Perrysburg and Sylvania, before joining U.S. 23 North into Michigan. Getting back to I-74, this can become a reality and it should happen. BTW, it'll definitely save motorists, commuters and truckers, alike, a lot of time and mileage, especially when commuting, between Cincinnati and Huntington. The people in West Virginia want this and it will also benefit Ohio, as well, especially in terms of bringing in new business, along I-74 East. At last count, it's majority rule, among the people in Ohio and they want this highway made, as soon as possible. Case and point, the Tea Party can get lost- the people rule and they say, opinion or not, BUILD THE HIGHWAY!!!

Popular posts from this blog

The story on how the unbuilt US 40 Expressway in Brownsville took 40 years to complete.

For nearly four decades, the four lane US 40 just east of Brownsville came to an abrupt end - shown in the photo above - at Grindstone Road in Redstone Township.   In the late 1960s, what was then the Pennsylvania Division of Highways (PennDOH) extended a new four lane alignment of US 40 eastwards from Broadway Street slightly over one mile to Grindstone Road where an incomplete diamond interchange was built.  Earlier in the decade, PennDOH had built a four lane US 40 in Washington County into Brownsville complete with a new crossing over the Monongahela River known as the Lane Bane Bridge.  This new highway and bridge allowed US 40 to bypass the older Intercounty Bridge and downtown Brownsville. 

After this new highway opened, nothing would happen to it for nearly forty years.  US 40 traffic would use the ramps for this planned diamond interchange and then jog on Grindstone Road briefly before continuing towards Uniontown on the original National Road. 
What is unknown (at least to…

The story of the Boy Scout Ramps on Interstate 79 North in NW Pennsylvania

If you are traveling on Interstate 79 North of Pittsburgh, you may notice the remnants of a set of off and on ramps at mile 100 just north of Exit 99 (US 422).  There's a story behind these ramps.  Forty years ago, these ramps were built specifically for two Boy Scout Jamboree's that were held at Moraine State Park - 1973 and 1977.  The ramps purpose were to provide access to the north shore of Lake Arthur where the bulk of the festivities and campsite for the Jamboree were located.  (Lawrence County Memories has a great write up and map of the festivities on its site.)

Not long after the Jamboree ended the ramps were abandoned.  There are still remnants of the Boy Scout Ramps today.



Above: Sattelite view of the Boy Scout Jamboree Ramps. 
Below: A view of the ramps from I-79 South.



The google street view image above gives a view along West Park Road of where the set of ramps intersected the highway.  The ramps provided direct access to North Shore Drive (which is the right tur…

The few clues of the Northern Durham Parkway

Sometimes when you look through a box of maps for the first time in five years, you come across something you may have easily over looked.  Such was the case when I found a 2004 (so rather recent) map of Raleigh.  This map was made by the Dolph Map Company for WakeMed.  In the Northwestern corner of Wake County, there were two items to the map showing roads that are still not in existence 13 years later.

The road is the Northern Durham Parkway - this is a proposed 19 mile highway from US 501 north of Durham to the Raleigh-Durham International Airport.  The first proposals for this highway date back to 1967 when Eno Drive-Gorman Road was listed on the Durham Area Thoroughfare Plan. (1)  Other proposals called the highway the Northwest and Northeast Durham Loop. (2)  The route would serve as a northern and eastern bypass of Durham almost serving as a near loop.  The route was fought vigorously for three decades by the Eno River Association citing concerns for the the Eno River, nearby n…