Greensboro, NC: Interstate Construction Central

On June 17, NCDOT plans to let the next construction project for its Greensboro Loop project, the northeast segment from US 70 to US 29. When work starts sometime later in the summer, this will be the third interstate construction project to get the go-ahead in the Greensboro/Guilford County, NC area in the past six months. Over the next few years this will make the Triad Area on North Carolina one of the busiest places for road construction in the country.

A Breakdown of the Interstate Construction Projects:
1. Greensboro Loop, NW Segment, from Bryan Blvd. to Battleground Ave. (US 220).
Contract Number: C203197
Length: 3.8 Miles
Cost: $122,804,388.50
Construction started: October 30, 2013
Estimated completion: March 14, 2018 

This project to build the next segment of I-840 from Bryan Blvd. to Battleground Avenue has been underway since last year. So far, the project has been noticeable due to all the land cleared for the future roadway. When finished I-840 will be extended to US 220 and the western half of the project will be nearly finished. The project had an added benefit, since the contract includes updating signage along the existing Loop, showing the future I-73 signage to be placed along the Loop and along Bryan Blvd. to the PTI Airport interchange. The sign changes will also occur along I-40, as this plan image shows:
 The destinations, or control cities for I-73 will be the Airport and Martinsville, VA. Also I-73 exit numbers will be applied to the existing exits south of Bryan Blvd. West Friendly Ave., currently exit 3 will become Exit 104, and Bryan Blvd. will become Exit 107:

Apparently, NCDOT feels that since I-73 leaves the Loop it should exit itself, instead of I-840 getting the exit number. The plans also revealed the exit number for the PTI Airport exit will be 109:
This exit ramp will then split giving the Airport traffic a separate ramp to use:

The contract will also replace the current Future I-73/I-840 signs with similar ones with interstate shields.
The northern end of the project will be the interchange with US 220 as the sign plan indicates:
 
2. Future I-73 from Existing SR-2085 (Bryan Blvd) / Airport Pkwy Interchange to South of US-220 Near Haw River.
Contract No.: C203433

Length: 9.4 Miles
Cost: $176,550,000.00
Construction started: May 7, 2014
Estimated completion: April 25, 2017

This project combined two previous projects the first to build the 'NC 68-US 220 Connector' that would take I-73 about 7 miles from north of the PTI Airport to US 220 near Summerfield and the 'I-73 Connector' to take I-73 from NC 68 to Bryan Blvd at the Airport exit. The NC 68-US 220 Connector project has been planned for years, however, the I-73 Connector project only gained approval within the last year and was pushed along by Airport interests who wanted a new taxiway that will be built as part of the project. The project is a Design-Build contract so no plans were released when the project was let. The published Request for Proposal documents, however, indicate that the tie-in between the two projects along NC 68 will not be an upgrade of the existing expressway, but the building of 2 parallel roadways for I-73 traffic on either side. The complete set of available documents for the project can be found on the contract's Letting Details website.

3. Greensboro Loop, NE Segment, from US 70 to US 29.
Contract Number: C203399
Length: 5.5 Miles
Cost: $119,000,000 (Est.)
Construction to start: July 2014
Estimated completion: Spring 2018

This is the second of three projects to build the eastern-half of the Greensboro Loop. This segment will continue the existing 2 mile segment that connected I-40/I-85 to US 70 about another 6 miles to US 29. NCDOT has gotten permission to sign both open segments of the Loop as I-840. Apparently though, to prevent any confusion as to 2 different I-840s before the entire Loop is completed, NCDOT will sign this segment only as I-785. NCDOT received permission from the FHWA for this designation in 2013. As the plan images below show, the signs will be designed to eventually have an I-840 shield also. Here's the future signage at the current split of I-40 East and I-85 South at the Loop:
Here's signage on the opposite side of the Loop for I-40 East:

There will be two exits on the new segment, the first for Huffine Road:

The second for US 29, with US 29 North being the future route of I-785 and where it will leave the loop (hence future panels in this exit sign plan):

It seems unlikely that I-785 will be signed along US 29 until well after the Loop is constructed. Sign plans for US 29 at the Loop interchange, one that reveals future exit numbers with US 29 mileposts, seem to confirm this:


A full description of the Greensboro Loop projects can be found at NCDOT's Greensboro Urban Loop site.

Given these three projects, and the start of the Winston-Salem Northern Beltway (Future I-74) construction early next year in next-door Forsyth County, this will be an area highway construction enthusiasts will want to monitor for, at least, the next four or five years.

Comments

Popular posts from this blog

The New PA 48 - The Unbuilt Eastern Allegheny County Freeway

From the 1950's to the 1980's, there was a proposal to build a 4-lane expressway paralleling PA Route 48.  This proposed highway was officially known as the "North-South Parkway", but locally known as the "New 48".  Sadly, this route never came to be; however, it is the predecessor of another highway, The Mon-Fayette Expressway.  The "New 48" was a highly debated route that really never got beyond the planning stages.  There are very few remnants of construction left.

History:
Originally proposed in the post-war Pittsburgh, the "New 48" was a lot of talk, but it really never saw much work done.  Most of the discussion, planning, land acquisitions and right-of-way clearing occurred in the 1960s.  The "New 48" would also have gone by the term "North-South Parkway".  This was the term for the highway used in White Oak: A Master Plan done by the Pittsburgh Regional Planning Commission in 1960. (1)

The early 60s would see muc…

Hunting for forgotten history; Old US 99 in Fresno

Coming back from my Great Lakes Trip the other day I encountered this sign goof at Fresno-Yosemite International Airport which incorrectly displays US Route 99.





That little US 99 sign was the inspiration I needed to start tracking all the former alignments through the City of Fresno.  Fresno in general has had a huge shift in highway layouts over the decades which is something I intend to finish with California 41 and 180 perhaps later this month.  Based off my research I came with the following three maps progressing northward through Fresno showing every iteration of US 99 before it was downgraded to a State Highway in 1967.




Essentially the route alignment history of US Route 99 in Fresno is as follows.

1926-1930 Alignment 

Progressing northward into Fresno US Route 99 would have followed:

Railroad Avenue
-  Cherry Avenue
-  Broadway Street
-  Divisadero Street
-  H Street
-  Belmont Avenue
-  Golden State Avenue

1930-1934 Realignment off of Railroad Avenue

Sometime between 1930 to …

The William Flinn (not Flynn) Highway - Pittsburgh's Misspelled Street

For decades if you traveled along PA Route 8 in Pittsburgh's North Hills suburbs, you would have noticed signs that read "William Flynn Highway" at every intersection.  Even today, many businesses and residences have their addresses listed as XXXX William Flynn Highway.  However, it's not William Flynn Highway, it is William FLINN Highway - and the gentleman who it is named for has a long and storied past in Pittsburgh's infrastructure history.

William Flinn was born in England in 1851; however later that year, his family emigrated to the United States and would settle in Pittsburgh.  A 10 year-old school drop out, Flinn grew interested in politics and would join the Allegheny County Republican Party in 1877 as a ward commissioner and a seat on the Board of Fire Commissioners.  Flinn would serve in the Pennsylvania State House of Representatives and Senate from 1877 to 1902. (1)

Flinn along with James J. Booth would found the Booth and Flinn construction firm in …