Skip to main content

The I-485 Blame Game

Yes, it's again time for the Interstate 485 blame game. And a recent article in the Charlotte Observer brings a whole litany of complaints, finger pointing, and disappointed drivers. So lets just list all of the complaints.

First, the section of I-485 from NC 16 to I-77 and NC 115 could end up opening two years behind its Spring 2007 original planned opening date.

So what went wrong? We've covered a few of them here at the blog.

The contractor Virginia Beach based Skanska lists their beefs:

First, when they were to begin surveying in December 2003. Not all of the land for the project had been owned by the State. The state counters with it is sometime common to have a few parcels of land not owned by the State at the start of construction. However, NCDOT does concede that the 14 parcels of land that in December 2003 were not purchased were a bit excessive.

Skanska claims that the lack of a completed right-of-way process forced them to access construction sites with more difficulty.

Other complaints from Skanska include the 62 extra days it took to move a major gas line along with five other utility relocation delays.

And finally the contractor contends that they did not receive plans to provide access to a Target and car dealership until the last minute and that the plans they received were hand drawn.

Skanska claims that the state has caused the project to be 311 days behind schedule, and has requested slightly over $8.5 million in additional compensation. The state, however, view the causes for the delays otherwise.

NCDOT feels that the contractor could have easily worked on other sections of the nearly six mile project while waiting for the utilities to be moved. They also do not believe that the company has not accurately computed their losses.

In addition, NCDOT points to a January 22nd letter that required Skanska to rebuild the asphalt base on the I-485/I-77 interchange ramps because it was too thin.

But the state does admit causing 138 days in delays.

Now onto the final segment of the loop. (I-77 to I-85 near Concord/University)

It still appears that the highway will not see any construction until 2015. It appears that a preliminary opening date is 2018. (Ten years from now). Considering the various funding, procedural, and construction delays, I'm willing to go out on a limb and say that it'll be 2021 before I-485 is officially done.

Now there is one ray of hope for completing I-485. Barry moose, who is the NCDOT engineer that oversees the Charlotte area, says that if the state can find the extra money to build the highway, construction could begin in 2011.

However, he didn't guarantee that if that would happen there would be no procedural or construction delays with it either.

Story: Charlotte Observer

Comments

Popular posts from this blog

The New PA 48 - The Unbuilt Eastern Allegheny County Freeway

From the 1950's to the 1980's, there was a proposal to build a 4-lane expressway paralleling PA Route 48.  This proposed highway was officially known as the "North-South Parkway", but locally known as the "New 48".  Sadly, this route never came to be; however, it is the predecessor of another highway, The Mon-Fayette Expressway.  The "New 48" was a highly debated route that really never got beyond the planning stages.  There are very few remnants of construction left.

History:
Originally proposed in the post-war Pittsburgh, the "New 48" was a lot of talk, but it really never saw much work done.  Most of the discussion, planning, land acquisitions and right-of-way clearing occurred in the 1960s.  The "New 48" would also have gone by the term "North-South Parkway".  This was the term for the highway used in White Oak: A Master Plan done by the Pittsburgh Regional Planning Commission in 1960. (1)

The early 60s would see muc…

Hunting for forgotten history; Old US 99 in Fresno

Coming back from my Great Lakes Trip the other day I encountered this sign goof at Fresno-Yosemite International Airport which incorrectly displays US Route 99.





That little US 99 sign was the inspiration I needed to start tracking all the former alignments through the City of Fresno.  Fresno in general has had a huge shift in highway layouts over the decades which is something I intend to finish with California 41 and 180 perhaps later this month.  Based off my research I came with the following three maps progressing northward through Fresno showing every iteration of US 99 before it was downgraded to a State Highway in 1967.




Essentially the route alignment history of US Route 99 in Fresno is as follows.

1926-1930 Alignment 

Progressing northward into Fresno US Route 99 would have followed:

Railroad Avenue
-  Cherry Avenue
-  Broadway Street
-  Divisadero Street
-  H Street
-  Belmont Avenue
-  Golden State Avenue

1930-1934 Realignment off of Railroad Avenue

Sometime between 1930 to …

The William Flinn (not Flynn) Highway - Pittsburgh's Misspelled Street

For decades if you traveled along PA Route 8 in Pittsburgh's North Hills suburbs, you would have noticed signs that read "William Flynn Highway" at every intersection.  Even today, many businesses and residences have their addresses listed as XXXX William Flynn Highway.  However, it's not William Flynn Highway, it is William FLINN Highway - and the gentleman who it is named for has a long and storied past in Pittsburgh's infrastructure history.

William Flinn was born in England in 1851; however later that year, his family emigrated to the United States and would settle in Pittsburgh.  A 10 year-old school drop out, Flinn grew interested in politics and would join the Allegheny County Republican Party in 1877 as a ward commissioner and a seat on the Board of Fire Commissioners.  Flinn would serve in the Pennsylvania State House of Representatives and Senate from 1877 to 1902. (1)

Flinn along with James J. Booth would found the Booth and Flinn construction firm in …