Pressure's on...Interstate 485 timeline in the hands of MUMPO

The Mecklenburg-Union Metropolitan Planning Organization last night heard from NCDOT officials on the impacts of their upcoming August decision on Charlotte transportation priorities.

NCDOT officials warned that if the completion of Interstate 485 is not the top priority of MUMPO - the project may not start until 2015.

Currently, MUMPO has the upgrade of 1.4 miles of Independence Blvd. to an expressway as their top construction priority. Construction of that project is set to begin in 2011.

In order to build the remaining miles of the I-485 Outer Loop sooner, funding from other projects would have to be moved into that project and the over $150 million improvements to Independence Blvd. (US 74) would make that happen.

In her 2008 campaign, Governor Beverly Perdue promised that construction of the missing I-485 link would begin in 2009 with completion in 2011 or 2012.

A blessing from MUMPO on I-485 would make it easier to move funds to that project.

MUMPO officials don't seem convinced after last night's meeting.

“We expected additional resources,” said Charlotte City Council member Anthony Foxx, a MUMPO member.

Weddington Mayor Nancy Anderson said Perdue “left her checkbook at home.”

Story Link:

DOT Official: Another I-485 delay possible ---Charlotte Observer

Commentary:

Well, the political pressure from Raleigh will be hard and heavy on MUMPO members - as this was a big deal in Gov. Perdue's campaign. Throw in a strong distaste of many Charlotteans for Raleigh - in the various delays and political games with this route - makes this a very important decision. Not only for those in Charlotte, but for a number of people in Raleigh, too.

Comments

Popular posts from this blog

The Relief Route That Wasn't: The Never Built I-70 Bypass in the Mid-Mon Valley

In June 1963, a small blurb in the Pittsburgh Post-Gazette read that The Westmoreland Engineering Company was awarded a $24,060 bid to study the proposed construction of Interstate 70 in Westmoreland and Washington Counties.  The study was to see what the construction and right-of-way costs "...to modernize the existing highway to Interstate requirements within eight months." (1)  This small, non-attributed, three paragraph article came less than a decade after the completion of a four lane highway that linked the Mid-Mon Valley to the Pennsylvania Turnpike. This would be the start of a 15 year process to upgrade and improve Interstate 70 - a process that ultimately never produced a single foot of new highway.

This is the story, albeit brief, of the I-70 that never came about.

Background:
What is now known as Interstate70 from Washington to New Stanton began as a connecting highway for the region to the Pennsylvania Turnpike.  Known as the "Express Highway", construct…

A look at Pittsburgh's Saw Mill Run Boulevard

Saw Mill Run Boulevard - Pennsylvania State Route 51 - runs through the narrow Saw Mill Run Valley.  It begins at the intersection of Clairton Road and Provost Road at the City of Pittsburgh Line with Brentwood.  It ends at the West End Circle at the entrance to the West End Bridge.  A four lane highway for its the entire length, Saw Mill Run Boulevard consists of interchanges at the South Portal of the Liberty Tubes and with the Parkway West.  It is an expressway from the Parkway to the West End Circle (West End Bypass).  One of the most well known traffic tie-ups in the Pittsburgh area occurs between Maytide Street and PA 88 (Library Road) which is simply known as 'Maytide and 88.'

History:
Saw Mill Run Boulevard was part of the 1928 Allegheny County 'City Beautiful' bond issue.  The bonds resulted in the creation of Saw Mill Run, Ohio River, Allegheny River and Mosside Boulevards. (1)   After the completion of the Liberty Tunnels in 1924, Downtown Pittsburgh was offic…

The Many Failed Plans of Pittsburgh's Wabash Bridge and Tunnel

The December 27, 2004 opening of the Wabash Tunnel ended over 70 years of proposals and speculation for the use of the over 100 year old facility.  The tunnel, which is now a reversible roadway that is an alternative route for rush hour traffic, saw many failed plans during the 20th Century.  These plans included options for mass transit, converted and new bridges for vehicles, and other forms of transportation.

Brief History:
Constructed in 1902-04, the Wabash Bridge and Tunnel was planned and financed by rail mogul, Jay Gould.  Gould began his "Battle of the Wabash" with the established railroads of the city in 1890.  He would finally emerge victorious, but during that struggle, Gould would see many setbacks that would eventually result in the railroad's bankruptcy in 1908.  On October 19, 1903, when the two ends of the bridge were to be joined together over the Monongahela River, the 109' bridge collapsed; killing ten men.  Construction would resume four days later …