A Columbus Day Construction Progress Trip

I took a trip on Monday to see what progress, if any, had been made in some of the highway projects I am following starting in Durham then heading west on US 64 to Asheboro, northon US 220 to Greensboro then back east to Durham on I-40/85.
1. The Triangle Parkway
Construction it appears has finally begun with the start of clearing of the toll road's right-of-way. The evidence is at the northern end and does not extend south to the Davis Drive (still under construction to make it a 4-lane highway) interchange on NC 540:
View heading south on NC 147 just before it turns to end at Alexander Drive.
Closer view of the area cleared and the construction equipment.
Meanwhile, all was quiet at the other end of the construction corridor where the Parkway will meet NC 540 (mostly hidden y the grass under the ramp bridges).

2. The Future I-73 (US 220)/I-74 (US 311) Interchange:
I drove northbound from Asheboro and took a few shots of progress in clearing the construction zone for the interchange over the past month:
The first clearance area, this will be for the off-ramp taking I-74 West toward High Point.
The second clearance area where the route signage is located is for construction of the flyover ramp that will take I-74 West over I-73. Here's a better look:
The cleared area may be piled with more dirt if the ramp has to be higher. Lastly, the 3rd construction area...
This will be where the flyover and onramp from I-74 East to I-73 (US 220) north will be built.

3. Some new signage in Greensboro:
I drove through Death Valley on the way back to Durham to take some photos of the new signs and or exit numbers heading east on I-40:
Here's the first new I-40 exit for Randleman Road, this number was for US 220 when I-40 was on the Loop, now it's less interesting.
The once unique six-shield sign assembly, is now down to 5. There are even fewer shields on the overhead signs-
US 421 North used to be on what is now Exit 223 and 421 South on what is now Exit 222.
The shield signs were finally corrected in August, I still don't see the need for Business 85 here.
And finally, a dichotomy of exit numbers--
The I-40 one is on the right, but the next exit is with I-85 mileposts. It would be nice if you could travel 95 miles in the equivalent of a 1/2 mile according to the sign, but then I'd miss exiting to Durham.

Comments

Anonymous said…
I'm glad they finally move on with the future I-73/I-74 interchange.. if only if they can just work on the section through Asheboro asap.
Bob Malme said…
The Asheboro work is to be let next year. The letting actually has been moved up three months to next June. This means work could start as early as July 2010. It will be interesting to see which project is completed first, and what this does to changing out the Future Interstate signs along US 220 north and south of the I-74 interchange.
Anonymous said…
that is a great news! They need to get that section done too.. hopefully they can finish the entire route and have both interstates signed in NC by at least 2030. (Cant say for other states except SC whom is now getting so involved with trying to build I-73 from NC border to Myrtle Beach.)

Popular posts from this blog

Goodbye Interstate 495; Hello Interstate 87

It seems like yesterday when I blogged about new Future Interstate 495 signs that were going to be installed along US 64 along the Knightdale Bypass and along the way to Rocky Mount.  Well after just three years, Interstate 495 is officially no more.  This week NCDOT crews began to install Interstate 87 shields along the Raleigh Beltline and Knightdale Bypass from Southeast Raleigh to Rolesville Road in Wendell.  The new interstate designation follows Interstate 440 west from I-40 near Garner leaving the Beltline at the Knightdale Bypass and following US 64/264 about another 12 or so miles until the six lane portion of the Knightdale Bypass ends just beyond Business US 64.

Eventually, Interstate 87 will continue east along US 64 past Zebulon, Rocky Mount and Tarboro to Williamston where it will head north and northeast along US 17 into Virginia and Norfolk.  The new signs reflect the first official section of Interstate 87 in North Carolina - as the Knightdale Bypass meets national I…

The story on how the unbuilt US 40 Expressway in Brownsville took 40 years to complete.

For nearly four decades, the four lane US 40 just east of Brownsville came to an abrupt end - shown in the photo above - at Grindstone Road in Redstone Township.   In the late 1960s, what was then the Pennsylvania Division of Highways (PennDOH) extended a new four lane alignment of US 40 eastwards from Broadway Street slightly over one mile to Grindstone Road where an incomplete diamond interchange was built.  Earlier in the decade, PennDOH had built a four lane US 40 in Washington County into Brownsville complete with a new crossing over the Monongahela River known as the Lane Bane Bridge.  This new highway and bridge allowed US 40 to bypass the older Intercounty Bridge and downtown Brownsville. 

After this new highway opened, nothing would happen to it for nearly forty years.  US 40 traffic would use the ramps for this planned diamond interchange and then jog on Grindstone Road briefly before continuing towards Uniontown on the original National Road. 
What is unknown (at least to…

Hunting for forgotten history; Old US 99 in Fresno

Coming back from my Great Lakes Trip the other day I encountered this sign goof at Fresno-Yosemite International Airport which incorrectly displays US Route 99.





That little US 99 sign was the inspiration I needed to start tracking all the former alignments through the City of Fresno.  Fresno in general has had a huge shift in highway layouts over the decades which is something I intend to finish with California 41 and 180 perhaps later this month.  Based off my research I came with the following three maps progressing northward through Fresno showing every iteration of US 99 before it was downgraded to a State Highway in 1967.




Essentially the route alignment history of US Route 99 in Fresno is as follows.

1926-1930 Alignment 

Progressing northward into Fresno US Route 99 would have followed:

Railroad Avenue
-  Cherry Avenue
-  Broadway Street
-  Divisadero Street
-  H Street
-  Belmont Avenue
-  Golden State Avenue

1930-1934 Realignment off of Railroad Avenue

Sometime between 1930 to …