Skip to main content

I-74 Construction November Road Trip Report

So I wouldn't stew over Duke's loss to UNC, or the lastest Canes loss, and with the forecast for sunny skies and a high of 74, I decided Sunday morning would be a good time to check out I-74 construction progress from High Point to Randleman, plus some extra points of interest.

Construction Progress since early October-
My first stop was Baker Road. It appears the underlying structure for the bridge is complete and all that is needed is for cement to be poured:
After the bridge is completed, the existing road will have to be widened and tied to the bridge, but that should not take long to do. Another sign of progress is the excavating of the freeway:
Further toward Baker Road, so that the existing temporary road can quickly be demolished once the bridge is completed. Another sign of progress can be seen in the distance, the first overhead sign gantry to be put up, this for the Business 85 exit (My y I-74 page will have a better photo).

Jackson Lake Bridge-
There's more work to be done here. While the eastbound lanes look almost ready, there remains much to be excavated along the westbound lanes:
There is still some utility work going on in this area and completion of the grading of the road may have to wait to be completed. There's much more progress seen when looking the other direction toward Kersey Valley Road:
The nearly completed roadbed continues up past the Kersey Valley Road bridge, where again, there still remains work to be done:
As you see, there's much excavation still needed to be done, but most has been deposited along a slope next to the eastbound lanes, which is now being seeded:
They are, however, starting to grade the rest of the roadbed from before the I-85 interchange back toward the bridge:
This is a view of the I-85 interchange bridges from the cut-off end of Dresden Road:
Most of the work on the flyover ramp from I-74 East to I-85 North is complete, you'll notice there's not much change from earlier images:
Progress, however, can be seen just south of the bridge where the pieces of support structures for overhead signs has been placed on the original northbound I-85 lanes now being detoured:
As for the flyover itself, there's still some work to do, with connection to the roadway and the construction of walls still needed to be finished:
The metal containers are on the future I-85 on-ramp to I-74 East. There are some signs of near completion not much further down the road, with gurdrail being installed. Such as can be seen in this photo from the Tuttle Road Bridge, also notice the grass medians:
Also close to completion is the Cedar Square Road bridge and new connection to US 311. The view going west on Cedar Square shows only minor work is needed to tie the existing road in to the new one:
On the opposite side the connection to the bridge is complete and traffic signals have been installed and turned on in yellow flashing mode:
The remainder of work needed here is to remove the existing Cedar Square roadway and excavate and grade the future freeway road surface once the new bridge is open:
Notice the recent layer of asphalt on the westbound lanes next to Poole Road. The left hand side is the beginning of the exit ramp, which can't be completed until the existing road is gone.

They are also making quick progress along US 220 on the next segment of construction, including the first piers for the flyover ramps:
And further clearing of the land for the interchange and I-74 freeway heading west:
I drove further south to see the progress of the new rest areas built on I-73/74 in Seagrove. According to the last Board of Transportation meeting minutes. These rest areas are suppose to open on January 2. There seems to be more progress on the northbound rest area than the south. Going south you are still restricted to one lane. The rest area building is behind trees up a hill, so I could not get a photo. But here's the view approaching the southbound off-ramp:
Sorry for the sun glare. The northbound rest area looks almost ready. All lanes are open going by northbound, here ia view with the rest area in the distance:
Here's the best image I could get of the building:
This building is closer to the highway. I should get better photos when it's open and I'm not going by at 70 mph.

Part of the reason for taking the trip was that I had heard from several contacts that work had been nearly completed in several areas, and maybe the route could open before the end of the year. From my observations and the photos there was some confirmation that parts are near completion, but as you saw, there is still much work needed in other places. Thus my optimistic guess is, if the winter is fairly dry, that the I-74 freeway from Business 85 to Cedar Square Road could open by late spring. Which means another visit to observe progress in December or January.

Comments

Anonymous said…
boy, they are surely building the flyover ramps quicker at the I-73 and I-74 interchange.. (it was nothing when i last went through 2 months ago).

I'm excited about how the I-73/I-74 projects have been going.
digger derricks said…
digger derricks I agree I go that way on the way to work, and they might as well not even be there!

Popular posts from this blog

The Relief Route That Wasn't: The Never Built I-70 Bypass in the Mid-Mon Valley

In June 1963, a small blurb in the Pittsburgh Post-Gazette read that The Westmoreland Engineering Company was awarded a $24,060 bid to study the proposed construction of Interstate 70 in Westmoreland and Washington Counties.  The study was to see what the construction and right-of-way costs "...to modernize the existing highway to Interstate requirements within eight months." (1)  This small, non-attributed, three paragraph article came less than a decade after the completion of a four lane highway that linked the Mid-Mon Valley to the Pennsylvania Turnpike. This would be the start of a 15 year process to upgrade and improve Interstate 70 - a process that ultimately never produced a single foot of new highway.

This is the story, albeit brief, of the I-70 that never came about.

Background:
What is now known as Interstate70 from Washington to New Stanton began as a connecting highway for the region to the Pennsylvania Turnpike.  Known as the "Express Highway", construct…

The Many Failed Plans of Pittsburgh's Wabash Bridge and Tunnel

The December 27, 2004 opening of the Wabash Tunnel ended over 70 years of proposals and speculation for the use of the over 100 year old facility.  The tunnel, which is now a reversible roadway that is an alternative route for rush hour traffic, saw many failed plans during the 20th Century.  These plans included options for mass transit, converted and new bridges for vehicles, and other forms of transportation.

Brief History:
Constructed in 1902-04, the Wabash Bridge and Tunnel was planned and financed by rail mogul, Jay Gould.  Gould began his "Battle of the Wabash" with the established railroads of the city in 1890.  He would finally emerge victorious, but during that struggle, Gould would see many setbacks that would eventually result in the railroad's bankruptcy in 1908.  On October 19, 1903, when the two ends of the bridge were to be joined together over the Monongahela River, the 109' bridge collapsed; killing ten men.  Construction would resume four days later …

A look at Pittsburgh's Saw Mill Run Boulevard

Saw Mill Run Boulevard - Pennsylvania State Route 51 - runs through the narrow Saw Mill Run Valley.  It begins at the intersection of Clairton Road and Provost Road at the City of Pittsburgh Line with Brentwood.  It ends at the West End Circle at the entrance to the West End Bridge.  A four lane highway for its the entire length, Saw Mill Run Boulevard consists of interchanges at the South Portal of the Liberty Tubes and with the Parkway West.  It is an expressway from the Parkway to the West End Circle (West End Bypass).  One of the most well known traffic tie-ups in the Pittsburgh area occurs between Maytide Street and PA 88 (Library Road) which is simply known as 'Maytide and 88.'

History:
Saw Mill Run Boulevard was part of the 1928 Allegheny County 'City Beautiful' bond issue.  The bonds resulted in the creation of Saw Mill Run, Ohio River, Allegheny River and Mosside Boulevards. (1)   After the completion of the Liberty Tunnels in 1924, Downtown Pittsburgh was offic…