The Washington (PA) Herald-Standard has some new reports on the progress of the Mon-Fayette Expressway in both Pennsylvania and West Virginia.

First, West Virginia has approved the plans on the toll plaza for WV 43 and construction is underway.  WVDOH plans to open the highway in the Spring of 2011.  As a result, PA 43 will now have a straight shot from Uniontown to Interstate 68.

On the Pennsylvania side, construction on the highway sections of the remainder of the Uniontown-to-Brownsville Link are well underway and ahead of schedule.  The Mon-Fayette highway bridge over the Monongahela River near Brownsville is schedule to be completed in 2012.

If the fast pace of the highway work continues, the Pennsylvania Turnpike Commission may consider opening parts of the highway prior to the Mon River bridge completion in the Spring of 2012.  This would most likely include: the opening of the high speed interchange with US 119 in Uniontown - creating a continuous freeway link in the area - and continuing the highway north another four miles beyond US 40 (Exit 22) to Bull Run Road (Exit 26) south of Brownsville.

Comments

Anonymous said…
The interchange with Route 119 is planned to be open by the end of this year. As of now, almost all work on the interchange is finished. A few signs need to be installed, but everything else, including line painting, is finished.
Anonymous said…
The Herald-Standard is from Uniontown, PA. Washington, PA's newspaper is the Observer-Reporter.
Edward said…
As of 6/1/2011 the link to the report is dead.

Popular posts from this blog

The story on how the unbuilt US 40 Expressway in Brownsville took 40 years to complete.

For nearly four decades, the four lane US 40 just east of Brownsville came to an abrupt end - shown in the photo above - at Grindstone Road in Redstone Township.   In the late 1960s, what was then the Pennsylvania Division of Highways (PennDOH) extended a new four lane alignment of US 40 eastwards from Broadway Street slightly over one mile to Grindstone Road where an incomplete diamond interchange was built.  Earlier in the decade, PennDOH had built a four lane US 40 in Washington County into Brownsville complete with a new crossing over the Monongahela River known as the Lane Bane Bridge.  This new highway and bridge allowed US 40 to bypass the older Intercounty Bridge and downtown Brownsville. 

After this new highway opened, nothing would happen to it for nearly forty years.  US 40 traffic would use the ramps for this planned diamond interchange and then jog on Grindstone Road briefly before continuing towards Uniontown on the original National Road. 
What is unknown (at least to…

The story of the Boy Scout Ramps on Interstate 79 North in NW Pennsylvania

If you are traveling on Interstate 79 North of Pittsburgh, you may notice the remnants of a set of off and on ramps at mile 100 just north of Exit 99 (US 422).  There's a story behind these ramps.  Forty years ago, these ramps were built specifically for two Boy Scout Jamboree's that were held at Moraine State Park - 1973 and 1977.  The ramps purpose were to provide access to the north shore of Lake Arthur where the bulk of the festivities and campsite for the Jamboree were located.  (Lawrence County Memories has a great write up and map of the festivities on its site.)

Not long after the Jamboree ended the ramps were abandoned.  There are still remnants of the Boy Scout Ramps today.



Above: Sattelite view of the Boy Scout Jamboree Ramps. 
Below: A view of the ramps from I-79 South.



The google street view image above gives a view along West Park Road of where the set of ramps intersected the highway.  The ramps provided direct access to North Shore Drive (which is the right tur…

The few clues of the Northern Durham Parkway

Sometimes when you look through a box of maps for the first time in five years, you come across something you may have easily over looked.  Such was the case when I found a 2004 (so rather recent) map of Raleigh.  This map was made by the Dolph Map Company for WakeMed.  In the Northwestern corner of Wake County, there were two items to the map showing roads that are still not in existence 13 years later.

The road is the Northern Durham Parkway - this is a proposed 19 mile highway from US 501 north of Durham to the Raleigh-Durham International Airport.  The first proposals for this highway date back to 1967 when Eno Drive-Gorman Road was listed on the Durham Area Thoroughfare Plan. (1)  Other proposals called the highway the Northwest and Northeast Durham Loop. (2)  The route would serve as a northern and eastern bypass of Durham almost serving as a near loop.  The route was fought vigorously for three decades by the Eno River Association citing concerns for the the Eno River, nearby n…