Henry County (VA) I-73 Alternative Route Environmental Study Complete - with positive reviews

VDOT has completed the Environmental Assessment for the Henry County I-73 Alternative Route.  This route was pushed forward by the Henry County Board of Supervisors in 2007, VDOT released a preliminary impact study of the route in 2009, and the Commonwealth Transportation Board directed VDOT to do an environmental assessment of the alternative routing that December.

Henry County Supervisors had urged the study and possible routing as it ran I-73 closer to Martinsville's eastern edge.  The HCBoS plan would run about two miles longer and appears to cost more.

The alternative routing would utilize five miles of the existing US 58 bypass to the south and east of Martinsville.  That portion of the freeway would need to be upgraded to Interstate standards.  The initial planned alternative ran I-73 further to the east and parallel to US 220 and the southeast corner of the US 58 Bypass.  Both routes would meet north of I-73's junction with VA 87 east of Ridgeway.  The map at right drawn by the Martinsville Bulletin shows the two of the possible I-73 Henry County Routes.  The HCBoS route is red, the original VDOT proposal is in grey.  To my knowledge, this is the first clue of how I-73 will be routed south of Roanoke.

There is a third possible alternative route.  A modified version of the Henry County Alternative would eliminate two grade separations with the Norfolk Southern Railway and be about two tenths of a mile shorter.

Henry County officials are pleased with the results of the study, and have been touting the minimal impact to Fisher Farm Park in Ridgeway.  However, Virginians for Appropriate Roads (VAR) will be sure to have a voice in the matter once the official study is released and open for public comment.    VAR is opposed to any new construction of Interstate 73, preferring upgrades to existing US 220.   As part of their decision to drop an appeal on the planning process for I-73, VAR has the ability to challenge any future studies for I-73 "...that if a Supplemental Environmental Impact Statement is done for the project, Virginians for Appropriate Roads may raise road improvements and access management alternatives with respect to U.S. 220 in any judicial review challenge that the group might bring..."

VDOT has announced a open forum public hearing on the Henry County Alternative Route Study at the end of the month.  It will be held Tuesday, March 29 from 4-6 PM at the Laurel Park Middle School - 280 Laurel Park Ave. - in Martinsville.

Story Links:
I-73 assessment complete ---Martinsville Bulletin
I-73 study results are praised ---Martinsville Bulletin

Comments

Popular posts from this blog

The Relief Route That Wasn't: The Never Built I-70 Bypass in the Mid-Mon Valley

In June 1963, a small blurb in the Pittsburgh Post-Gazette read that The Westmoreland Engineering Company was awarded a $24,060 bid to study the proposed construction of Interstate 70 in Westmoreland and Washington Counties.  The study was to see what the construction and right-of-way costs "...to modernize the existing highway to Interstate requirements within eight months." (1)  This small, non-attributed, three paragraph article came less than a decade after the completion of a four lane highway that linked the Mid-Mon Valley to the Pennsylvania Turnpike. This would be the start of a 15 year process to upgrade and improve Interstate 70 - a process that ultimately never produced a single foot of new highway.

This is the story, albeit brief, of the I-70 that never came about.

Background:
What is now known as Interstate70 from Washington to New Stanton began as a connecting highway for the region to the Pennsylvania Turnpike.  Known as the "Express Highway", construct…

The Many Failed Plans of Pittsburgh's Wabash Bridge and Tunnel

The December 27, 2004 opening of the Wabash Tunnel ended over 70 years of proposals and speculation for the use of the over 100 year old facility.  The tunnel, which is now a reversible roadway that is an alternative route for rush hour traffic, saw many failed plans during the 20th Century.  These plans included options for mass transit, converted and new bridges for vehicles, and other forms of transportation.

Brief History:
Constructed in 1902-04, the Wabash Bridge and Tunnel was planned and financed by rail mogul, Jay Gould.  Gould began his "Battle of the Wabash" with the established railroads of the city in 1890.  He would finally emerge victorious, but during that struggle, Gould would see many setbacks that would eventually result in the railroad's bankruptcy in 1908.  On October 19, 1903, when the two ends of the bridge were to be joined together over the Monongahela River, the 109' bridge collapsed; killing ten men.  Construction would resume four days later …

A look at Pittsburgh's Saw Mill Run Boulevard

Saw Mill Run Boulevard - Pennsylvania State Route 51 - runs through the narrow Saw Mill Run Valley.  It begins at the intersection of Clairton Road and Provost Road at the City of Pittsburgh Line with Brentwood.  It ends at the West End Circle at the entrance to the West End Bridge.  A four lane highway for its the entire length, Saw Mill Run Boulevard consists of interchanges at the South Portal of the Liberty Tubes and with the Parkway West.  It is an expressway from the Parkway to the West End Circle (West End Bypass).  One of the most well known traffic tie-ups in the Pittsburgh area occurs between Maytide Street and PA 88 (Library Road) which is simply known as 'Maytide and 88.'

History:
Saw Mill Run Boulevard was part of the 1928 Allegheny County 'City Beautiful' bond issue.  The bonds resulted in the creation of Saw Mill Run, Ohio River, Allegheny River and Mosside Boulevards. (1)   After the completion of the Liberty Tunnels in 1924, Downtown Pittsburgh was offic…