Road Trip Along I-73/I-74 Corridor

Last Sunday Adam Prince, Chris Allen, and myself took an extended road trip taking in the Future I-73 Corridor from southern VA to Greensboro, Future I-74 SE of High Point and I-73/I-74 south of Randleman to Ellerbe. I will post some comments and photos from the I-74 and I-73/74 around Asheboro portions of our trip and will post the rest of the information on a revised, and revived, version of my I-73/I-74 pages to appear in the near future on Gribblenation.com.

1. I-74 Construction between Cedar Square Rd and US 220--
As most of you know, construction on the last piece of I-74 to be built along the 'US 311 Bypass' is set to be completed in October. Observations taken from the road trip suggest this may now be an optimistic date. Work has moved along at the northern section of the construction area. The roadbed is paved south from Cedar Square Rd to at least a mile south. This was the case when I visited the area last October. Things aren't as complete further south--

As you can see, not only is the area not paved, the grading has not been completed. That is because the current roadbed of Branson Davis Rd is still in the way--

The roadbed cannot be demolished until the bridge is complete and traffic can be re-routed. Some good news here, this now looks like it may happen this weekend, based on an e-mail from a local source I got this afternoon. A closer look at the area west of the bridge shows a lot of work still needs to be done--
This is a view under the bridge towards the other bridge under construction at Walker Mill Rd. (more below). The Branson Davis bridge appeared close to completion, confirmed if it is to open this weekend:
We didn't know it at the time, but apparently we were apparently one of the last to travel across the now former Walker Mill Rd. bridge.:
The completed bridge is to the right with only some minor issues remaining. From Walker Mill the I-74 roadbed is paved heading south toward the future US 311 interchange. Here's a view back to the north showing that view:
The unpaved roadbed the photo was taken from is the future ramps to and from West I-74. A closer look at the unfinished ramps:
The bridge carrying US 311 was finished in 2010, work has been proceeding on a replacement railroad bridge that is using the old US 311 right of way. There was plenty of traffic at this future interchange location, prompting speculation whether traffic signals are a part of the design. 

South of the US 311 interchange we began to get more optimistic again. This is the scene at the Plainfield Rd. bridge looking southeast:
Asphalt picks up again and continues to the end of the project at US 220. The view to the northwest, though not as good, still holds promise:
While the roadbed is still not paved, it should be able to have pavement placed soon, perhaps when all the work at US 311 is completed. Here's the view looking back north from the next completed bridge at Heath Dairy Rd:
Here the roadbed is paved and work to landscape the median appears to be underway. What was most exciting was the view to the SE and the US 220 interchange. What are those things in the distance--
Signs! Or at least the future supports for signs going up at the end of the 311 freeway. What will be on those signs? A trip down through Asheboro provides some clues.

2. US 220 Through Asheboro
US 220 thru Asheboro has been under construction since 2010 to bring the highway up to interstate standards, or more accurately, what the FHWA has deemed close enough to allow the route (and the remaining future I-73/I-74 sections between Greensboro and Ellerbe) to be signed as full interstates. Unlike with I-74, there is optimism here this project can be completed on-time, by this November.
As can be seen in the photo above most of the work between the northern end of the work zone and NC 42 ( a couple miles south) has been completed. The remaining work in this area relates to signage--
Above are the supports for the future NC 42 interchange related signs that should look like this:



From the NCDOT signage plans. The left exit will be eventually removed in an additional project, currently unfunded, to improve safety through the Asheboro corridor. The only real work continuing is around the NC 42 exit. Here's a view approaching the off ramp:


And there's some work needed between the off and on-ramps as well:
The empty sign posts up ahead are for the next exit, US 64/NC 49. A view of that interchange:
Work is not completed on creating the center Jersey-barrier median that will be used in most of the corridor. The last section under construction is just south of the interchange:
Work has only just started on the median here. The bridge in the distance is for McDowell Rd. Just beyond construction is complete and you are now on I-73-74!
 
Or is it I-74/I-73, and why is I-74 heading the wrong direction. Oops. Here's what the new assemblies are supposed to look like, this one at the former start of the interstates beyond NC 134:
Yes, the shields are really huge, NCDOT spared no expense. Let's hope the rest that go up resemble these and not the first one. To totally convince you that you are on an interstate, mile markers begin--
And the milemarkers match the numbers on the new exit signs--
This is now formerly Exit 51. The rest of the exit signs south of here to Ellerbe should have their numbers switched by the end of the summer of 2013. Signs between I-74 in Randleman and the Asheboro construction area may get the new numbers when I-74 is completed. I will post additional photos and updates when my pages go back online.

UPDATE: Adam's photos from this trip can be found here.

Comments

Anonymous said…
I am very excited about NCDOT finally signing I-73/I-74 from Elliebe to Greensboro/High Point area. Now, I wonder what about I-74 from High Point to Winston-Salem (I-40)?

Popular posts from this blog

Paper Highways: The Unbuilt New Orleans Bypass (Proposed I-410)

  There are many examples around the United States of proposed freeway corridors in urban areas that never saw the light of day for one reason or another. They all fall somewhere in between the little-known and the infamous and from the mundane to the spectacular. One of the more obscure and interesting examples of such a project is the short-lived idea to construct a southern beltway for the New Orleans metropolitan area in the 1960s and 70s. Greater New Orleans and its surrounding area grew rapidly in the years after World War II, as suburban sprawl encroached on the historically rural downriver parishes around the city. In response to the development of the region’s Westbank and the emergence of communities in St. Charles and St. John the Baptist Parishes as viable suburban communities during this period, regional planners began to consider concepts for new infrastructure projects to serve this growing population.  The idea for a circular freeway around the southern perimeter of t

Hernando de Soto Bridge (Memphis, TN)

The newest of the bridges that span the lower Mississippi River at Memphis, the Hernando de Soto Bridge was completed in 1973 and carries Interstate 40 between downtown Memphis and West Memphis, AR. The bridge’s signature M-shaped superstructure makes it an instantly recognizable landmark in the city and one of the most visually unique bridges on the Mississippi River. As early as 1953, Memphis city planners recommended the construction of a second highway bridge across the Mississippi River to connect the city with West Memphis, AR. The Memphis & Arkansas Bridge had been completed only four years earlier a couple miles downriver from downtown, however it was expected that long-term growth in the metro area would warrant the construction of an additional bridge, the fourth crossing of the Mississippi River to be built at Memphis, in the not-too-distant future. Unlike the previous three Mississippi River bridges to be built the city, the location chosen for this bridge was about two

Huey P. Long Bridge (New Orleans, LA)

Located on the lower Mississippi River a few miles west of New Orleans, the Huey P. Long Bridge is an enormous steel truss bridge that carries both road and rail traffic on an old-time structure that is a fascinating example of a bridge that has evolved in recent years to meet the traffic and safety demands of modern times. While officially located in suburban Jefferson Parish near the unincorporated community of Bridge City, this bridge’s location is most often associated with New Orleans, given that it’s the largest and most recognizable incorporated population center in the nearby vicinity. For this reason, this blog article considers the bridge’s location to be in New Orleans, even though this isn’t 100% geographically correct. Completed in 1935 as the first bridge across the Mississippi River in Louisiana and the first to be built in the New Orleans area, this bridge is one of two bridges on the Mississippi named for Huey P. Long, a Louisiana politician who served as the 40th Gove