I-73/I-74 Year in Review 2016

While the year ended up on a disappointing note with the news that the plan to open a new segment of I-73 north of Greensboro by the end of 2016, promised by NCDOT last spring, had been postponed, work continued quietly on all existing projects with the promise of further funding for additional work in the soon to be published NC State Transportation Improvement Plan (STIP) for 2018-2027.

I-73

NCDOT announced last spring that it planned to open the new I-73 route from PTI Airport to US 220 near the Haw River by the end of the year. In the summer it was learned there were going to be delays in opening the segment from Bryan Blvd. to NC 68, but the section between NC 68 and US 220 would open in November. Alas, in early December word came that the entire segment would not open until spring, probably May. Work on this segment, as of mid-December is 92% complete and there are segments which appear to be close to completion, as this photo from AA Forum member Strider shows:


However, there are other areas where paving has not quite started yet:

Work near the PTI Airport has recently picked up, so there's optimism the spring completion date will be met. Here's the closest view of the PTI Taxiway bridge now complete over the Future I-73 lanes as seen from Bryan Blvd:

Work is also continuing at the other end with bridge being constructed for Future I-73 over NC 68:

Further north, the work on the segment along US 220 north to NC 68 has also progressed over the past year with the project now 72% complete, as opposed to almost 60% before. However, this segment is behind schedule with an opening date now listed as early 2018. Again, there are sections, such as at the Future I-73/US 220 interchange where work is almost complete:

And other areas where grading has just started, such as the future I-73 South lanes just south of the northern end of the project at NC 68:

Meanwhile, further south in Richmond County, significant progress has been made in upgrading US 220 to interstate standards as part of the I-73/I-74 Rockingham Bypass project. The work is, as of November, now over 60% complete, as compared to 34% a year ago. The project is still behind schedule though and the completion date was pushed back a month to April 2018. Most of the work has been building the service roads paralleling the existing roadway with traffic moved onto them so that the existing US 220 lanes can be improved, as seen in this photo by J. Austin Carter:
Traffic had been moved off the northbound lanes to the service road on the left in the photo above in December. Work also has been started at building the new interchange with Haywood Cemetery Road, here's the supports for the interchange overpass being constructed, also taken by J. Austin Carter:

As for the remainder of the Bypass, the good news is that that project is no longer on hold. It was added to the 2016-2025 STIP in February with construction scheduled to take place between 2022 and 2025. The prospects for completing I-73 in NC still rest with neighboring states with NCDOT not committed to building the northern and southern most segments without commitments by VA and SC to build their proposed routes.

I-74

While no new segment of I-74 started construction in 2016, there was positive news about the expansion of existing projects and new funding for others. Besides work on the Rockingham Bypass with I-73, work continued on the first segment of the Winston-Salem Northern Beltway between Business 40/US 421 and US 158. Progress is still slow, however, with the completion percentage in the past year only going from about 15% to just over 28% by year's end. The NCDOT Project page says the project should be 50.7% complete. Still work could be seen in clearing the path for the future road as seen in these photos from J. Austin Carter, both near Business 40:

And farther north at the project's northern end near US 158:

NCDOT announced that under a change in the state's transportation budget formula, all the remaining Eastern segments of the Beltway, and one segment of the Western Section would be funded under the new STIP with work to be completed by 2024. The STIP also includes funding for bringing US 74 up to interstate standards between Rockingham and Laurinburg. Work is to start on the segment between the two bypasses first with work scheduled to start in 2022. Work to bring the Laurinburg and Maxton Bypasses up to interstates standards should start soon after, as early as 2025.

Work also continues east of I-95 on a piecemeal basis to bring US 74 up to interstate standards. Work was completed this year on an overpass taking US 74 Business traffic over US 74 near Whiteville. Now the US 74 highway is limited access from four miles before the interchange with US 76 and the speed limit has been increased to 70 MPH, this is also the case at the northern end with the 70 MPH speed limit in place over five miles from the official end of I-74 at NC 41. Work is planned at several more intersections to replace them with interchanges, including at NC 130 over the next 10 years. There has been no word, however, as to whether US 74/76 east of Whiteville will be upgraded to interstate standards. NCDOT has, however, revived engineering work on the proposed Carolina Bays Extension project to extend SC 31 to US 17 just over the SC border.

2017 promises some new miles for I-73, and perhaps a few more funded projects when the new 2018-2027 State TIP is announced in January. And there may always be surprises. As always, I will have the latest information on my I-73/I-74 pages which, as of January 1, 2017, are on an new site, MalmeRoads.net.

All the Segment pages can be reached at http://www.malmeroads.net/i7374nc/index.html


Comments

Popular posts from this blog

The Relief Route That Wasn't: The Never Built I-70 Bypass in the Mid-Mon Valley

In June 1963, a small blurb in the Pittsburgh Post-Gazette read that The Westmoreland Engineering Company was awarded a $24,060 bid to study the proposed construction of Interstate 70 in Westmoreland and Washington Counties.  The study was to see what the construction and right-of-way costs "...to modernize the existing highway to Interstate requirements within eight months." (1)  This small, non-attributed, three paragraph article came less than a decade after the completion of a four lane highway that linked the Mid-Mon Valley to the Pennsylvania Turnpike. This would be the start of a 15 year process to upgrade and improve Interstate 70 - a process that ultimately never produced a single foot of new highway.

This is the story, albeit brief, of the I-70 that never came about.

Background:
What is now known as Interstate70 from Washington to New Stanton began as a connecting highway for the region to the Pennsylvania Turnpike.  Known as the "Express Highway", construct…

A look at Pittsburgh's Saw Mill Run Boulevard

Saw Mill Run Boulevard - Pennsylvania State Route 51 - runs through the narrow Saw Mill Run Valley.  It begins at the intersection of Clairton Road and Provost Road at the City of Pittsburgh Line with Brentwood.  It ends at the West End Circle at the entrance to the West End Bridge.  A four lane highway for its the entire length, Saw Mill Run Boulevard consists of interchanges at the South Portal of the Liberty Tubes and with the Parkway West.  It is an expressway from the Parkway to the West End Circle (West End Bypass).  One of the most well known traffic tie-ups in the Pittsburgh area occurs between Maytide Street and PA 88 (Library Road) which is simply known as 'Maytide and 88.'

History:
Saw Mill Run Boulevard was part of the 1928 Allegheny County 'City Beautiful' bond issue.  The bonds resulted in the creation of Saw Mill Run, Ohio River, Allegheny River and Mosside Boulevards. (1)   After the completion of the Liberty Tunnels in 1924, Downtown Pittsburgh was offic…

The Many Failed Plans of Pittsburgh's Wabash Bridge and Tunnel

The December 27, 2004 opening of the Wabash Tunnel ended over 70 years of proposals and speculation for the use of the over 100 year old facility.  The tunnel, which is now a reversible roadway that is an alternative route for rush hour traffic, saw many failed plans during the 20th Century.  These plans included options for mass transit, converted and new bridges for vehicles, and other forms of transportation.

Brief History:
Constructed in 1902-04, the Wabash Bridge and Tunnel was planned and financed by rail mogul, Jay Gould.  Gould began his "Battle of the Wabash" with the established railroads of the city in 1890.  He would finally emerge victorious, but during that struggle, Gould would see many setbacks that would eventually result in the railroad's bankruptcy in 1908.  On October 19, 1903, when the two ends of the bridge were to be joined together over the Monongahela River, the 109' bridge collapsed; killing ten men.  Construction would resume four days later …