Skip to main content

I-93 Signage Update

I took advantage of the first (and seemingly now, only) real good weather day of the week to take a quick road trip up I-93 north of Boston to check out the progress of the two sign replacement projects nearing completion. On my way, I checked out progress on the rehabilitation of the Neponset River Bridge which carries MA 3A from Quincy to Boston. Work has been going on for three years, and the work is now almost completed. Last week they opened all the lanes northbound...
Here's the view approaching Neponset Circle, not jammed with traffic as usual:
 The I-93 on-ramp, still with 1980s overhead signage (more below) lies just beyond. Meanwhile, while they still have restrictions southbound, new signage has gone up (and on the northbound side as well):
The 3A sign on the right seems to have some spacing issues at the top. The signs though are an improvement over the 1970s era signs they replaced.

I-93 Signage
A. Southern Project (Somerville to Wilmington)
Work on the southern project is almost completed. According to MassDOT the project was 84% complete as of a couple weeks ago. The remaining work appears to be related to regulatory signage. I noticed there was a need for more speed limit signs heading northbound. As for overhead signage, most appears up. For signs that had been placed prior to this past May, see my previous post. As for newer signage since then...
While the overhead signs above were there in June, the on-ramp signage to the right was old, it has since been updated. Both new overheads use the original gantries placed when I-93 opened in the 1970s. Some of the signage over both lanes, though, has been replaced by cantilevered versions for specific exits:
The MA 16 and MA 60 exits used to be on the same overhead, now they are on separated signs:
 Heading northbound, the other new signs south of I-95 that were not there in June are for the MA 28 Fellsway exit:
The signs in the distance on MA 28 were replaced as well, though one old one is still there. While the signage for Montvale Ave was up in June, it was blocked by the old sign that had not been taken down yet:
Besides putting the remaining signs up for the I-95/MA 128 exit, MassDOT has been busy repaving the highway in the area of the interchange:
MassDOT policy prohibits the placing of MA 128 shields on the overhead signs, so the 'publicly preferred' designation for the roadway gets auxiliary signs at each ramp entrance (well, almost, see below). This is the northbound assembly at the south I-95 off-ramp:
The South 128 sign is there, just out of frame. The Commerce Way exit signs are supplemented by portable message boards indicating when the next train will arrive.(not pictured)

Heading back southbound, here are the new I-95 signs (sorry for the picture quality going this direction):
Notice there's not auxiliary sign for MA 128 here, though there is at the North I-95 on-ramp:
The signs for the next two exits were largely in place in June. I was able, though to get a better photo of the new Park St exit sign and I-93 reassurance marker this time:
The rest of the signage southbound was new. Here is the Fellsway West exit signage heading toward Boston:
The MA 60 Exit sign now has a 'To MA 16 West' addition to complement the next exit which is only for MA 16 East:
In addition to 'Big Green Signs' MassDOT has installed Overhead Warning Signs as well (BYWS?), this for hieight restrictions in the Big Dig Tunnels (formerly on a ground mounted sign):
Meanwhile to the right, the project to complete a sound barrier wall along this section of I-93 has been completed. The auxiliary MA 16 sign at right is a holdover from before the sign replacement project. Here's the southbound signage for MA 16 East complementing the MA 16 West signage at MA 60:
The only other change to an exit sign contents is the now MA 38 exit which used to be MA 28/MA 38:
The '3 Mi/4 Min' variable message sign indicates the time to the Zakim Bridge. Good news to me, since when I went by northbound traffic was backed up to the MA 38 on-ramp. Here are the new overheads for the last two exits covered by this sign replacement contract:
The sign to the left is for the HOV lane that is restricted to 2+ occupant vehicles during the morning commute. Here's the signage just before the beginning of the HOV lane:
This is the last sign on a new overhead assembly. The final signs for Assembly Square are on the original gantries:
Though the contract officially runs to Exit 28 southbound, the sign for the Leverett Connector (MA 28/MA 3 North) is new as well.

B. Northern Project (Wilmington to NH Border):
This project is behind its southern counterpart. MassDOT indicated it was 79% complete as a couple weeks ago. There are still some older overhead assemblies present and places where only the new vertical sign supports have gone up. Still, this is great progress over last May when no new overhead signs were present.
Here's the first new signage northbound for  Concord St in Wilmington:
The new I-93 North reassurance marker is partly hidden by the white SUV on the right. The next new signs are for  the MA 62 and MA 125 exits:
Here's a view of the signage at the MA 125 off-ramp:
Notice the orange tag referencing the new sign placement in back, this implies this sign was put up recently. Another example of new MassDOT Big Yellow Warning Signs is northbound before the lane drop in Andover:
A relatively new I-93 mile marker is below the sign, hopefully in the next few years to reflect a new exit numbering system for the highway. The next big interchange is with I-495 near Lawrence, here given a 2-mile advance sign just before the MA 133 exit:
Here are the new signs at the I-495 interchange itself:
The last new signs I checked out northbound were for MA 110/MA 113 and River Road just before I-93 crosses the Merrimack River:
While turning around I got a photo of the typical I-93 on-ramp signage in this area:
Typically these 'Mass. Guide Signs' have 2 destinations, but all the I-93 southbound ones I've seen just indicate Boston. 

Heading southbound, here's an example of new signs still needed to be put up just before the I-495 exit:
One of the vertical posts for the new overheads can be seen on the right. Given the lack of I-93 signage on overheads heading north, I assume the new overheads will just have I-495 exit related information. Here's another photo heading south showing a new sign for the MA 125 exit and the fall foliage in the Andover area:
One of the last new highway overheads heading south for this part of the project is at the ramp for MA 125 previewing the MA 62 exit ahead:
Both projects will hopefully be wrapped up by the end of the year (they were supposed to be completed this past summer and MassDOT lists them as inactive (completed) projects). Since the same contractor is responsible for the I-93 replacement project south of Boston, which has barely been started in the year since it was let, hopefully the completion of these two contracts will allow resources to be shifted south. When there is progress on I-93 between Boston and Randolph, I will post an update.

Comments

Popular posts from this blog

California State Route 49; The Golden Chain Highway (CA 41 north to CA 16)

Last year I traveled California State Route 49 from CA 16 north to CA 89 in one continuous trip.  The prior two years I traveled the rest of CA 49 south to CA 41 in Oakhurst.  This blog post consists of photos of the highway from that time period and historical information about the southern part of CA 49.






This blog post is meant to be a continuation of the previous one I did regarding CA 49 from CA 16 north to CA 89.  A link to said blog post can be found below:

California State Route 49; The Golden Chain Highway (CA 16 north to CA 89)

As stated in the previous blog post; CA 49 is an approximately 295 mile long north/south highway which traverses the traditional Gold Rush Country of California.  While I intend to discuss county level historical alignments of CA 49 as I did in the first blog post I thought this would be a good place to discuss the backstory of highway. 

CA 49 was first signed in 1934 along a series of Legislative Route Numbers ("LRN") that were largely locate…

Throwback Thursday - April 26, 2018

This week's Throwback Thursday takes us to a throwback that never was. Interstate 291 was planned to be a loop around the west and north sides of Hartford, Connecticut, but for a number of reasons, such as community opposition and environmental issues put the kibosh on the proposal. However, there are a few places to check out parts of I-291 that were built, such as the existing stretch of I-291 in Windsor and Manchester. What was to be the interchange between I-84 and I-291 was built in Farmington, along with the ramps, but most of the ramps and through carriageways were never opened to the public. I visited in April 2008 and took some photos. In the distance, you can see the stack interchange with I-84 that was built but never put into operation.




Sources and Links:
Kurumi.com - I-291

Alaskan Way Viaduct Legacy Part 2; Alaskan Way, US Route 99 and the Alaskan Way Viaduct

Upon my arrival in downtown Seattle after taking the Bremerton-Seattle Ferry across Puget Sound I stopped to see the soon to be razed Alaskan Way Viaduct.  The Alaskan Way Viaduct is an elevated freeway and a former segment of US Route 99.  Interestingly US 99 is still signed at the southbound Viaduct Ramp located at Columbia Street and 1st Avenue in Pioneer Square.






This blog entry is the second in a series of two related to transportation in Seattle related to the Alaskan Way Viaduct.  The first entry in the series can be found here:

Alaskan Way Viaduct Legacy Part 1; Alki Point, Duwamish Head and Railroad Avenue

Continuing from the previous blog entry I mentioned Railroad Avenue as a major planked wood road corridor spanning Elliott Bay and the Waterfront of downtown Seattle.  By the early 20th century it was fairly obvious the wooden plank road was woefully inadequate for Automobile traffic. When US Route 99 was plotted out in 1926 it appears to have likely used the following route …